INSP-Final Inspection | 9/16/2009 | 9/17/2009 | 9/17/2009 | A | PASS |
Forrest France
|
|
|
Correction item field verified for completion, fire sprinkler permit finaled.
|
INSP-Final Inspection | 9/9/2009 | 9/10/2009 | 9/10/2009 | A | FAIL |
Forrest France
|
|
|
Still missing fire sprinkler head at one closet, temporary shelving is not acceptable.
|
INSP-Final Inspection | 8/28/2009 | 8/31/2009 | 8/31/2009 | A | FAIL |
Troy Cobbley
|
|
|
Still missing the pendant head in the closet
|
INSP-Final Inspection | 8/25/2009 | 8/26/2009 | 8/26/2009 | A | FAIL |
Troy Cobbley
|
|
|
Blocked pendants in closets
|
INSP-Sprinkler Rough-in | 5/26/2009 | 5/26/2009 | 5/26/2009 | A | PART |
Forrest France
|
|
|
Overhead rough-in okayed as noted.
|
INSP-Sprinkler Rough-in/Hydro | 5/22/2009 | 5/22/2009 | 5/25/2009 | P | PART |
Forrest France
|
|
|
See inspection comments per T. Frost.
|
INSP-Sprinkler Rough-in/Hydro | 5/20/2009 | 5/21/2009 | 5/21/2009 | A | FAIL |
Forrest France
|
|
|
Need to remove two upright heads at the 1st level, plans on site do not reflect field installation.
|
INSP-Sprinkler Rough-in | 5/19/2009 | 5/20/2009 | 5/20/2009 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled due to being overbooked.
|
FIR-Aging Inspection | 4/9/2009 | 4/9/2009 | 4/9/2009 | | DONE |
Forrest France
|
|
|
Work in progress, construction underway.
|