INSP-Final Inspection | 3/27/2009 | 3/27/2009 | 3/27/2009 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 3/19/2009 | 3/20/2009 | 3/20/2009 | A | PART |
Forrest France
|
|
|
Final pending project related fire alarm work for riser supervision. Discussed additonal items for final including backflow cert., calc. sticker, tags, outside bell test, final walkthrough, etc.
|
INSP-Supply line flush | 3/12/2009 | 3/12/2009 | 3/12/2009 | P | PART |
Forrest France
|
|
|
Forward flow testing of the backflow preventer completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 3/11/2009 | 3/11/2009 | 3/11/2009 | P | PART |
Forrest France
|
|
|
Rough-in corrections noted, discussed forward flow testing date 3/12 pm.
|
INSP-Supply line flush | 3/2/2009 | 3/3/2009 | 3/3/2009 | A | PART |
Forrest France
|
|
|
Underground fire supply line flush completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 3/2/2009 | 3/2/2009 | 3/2/2009 | P | PART |
Forrest France
|
|
|
Overhead rough-in completed okay with the exception of two mixed response heads at the concealed canopy area to be replaced, missing expansion tank for the antifreeze system, some items at the riser are not yet finished.
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2009 | 3/2/2009 | 3/2/2009 | A | PART |
Forrest France
|
|
|
Both the underground supply pipe and overhead wet and antifreeze systems passed hydrostatic testing.
|
INSP-Supply line flush | 2/17/2009 | 2/18/2009 | 2/18/2009 | P | PART |
Forrest France
|
|
|
UG fire supply line approved for bury including ductile riser.
|