Permit Information
Permit NumberFIR08-00863
StatusFinaled
Name COMMERCIAL FIRE PROTECTION
Site Address 2207 W OVERLAND RD
Project NameSAMMY'S
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of a new wet pipe and new antifreeze system to protect an existing building that is being changed from a print shop into a youth lounge.

(SAMMY'S) Permit to convert an existing printing shop ("B") to a new youth lounge ("A-2"). Space will be used for assembly purposes. This use is defined as an A-2 occupancy. Work to include: [installation of interior non-bearing walls to create one office, two accessible restrooms, one utility closet, and an open lounge area,] installation of a 60 square foot platform, installation of new doors and associated hardware, new plumbing, new electrical, and installation of interior finishes in compliance with chapter 8 of the IBC. This building is required to be sprinklered under a separate permit pulled threw Boise City Fire Dept. in compliance with the NFPA 13 standard. Planning approval by Josh Wilson per DRH08-00354.**TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/27/20093/27/20093/27/2009APASS
DetailsForrest France
Fire sprinkler permit finaled.
INSP-Final Inspection3/19/20093/20/20093/20/2009APART
DetailsForrest France
Final pending project related fire alarm work for riser supervision. Discussed additonal items for final including backflow cert., calc. sticker, tags, outside bell test, final walkthrough, etc.
INSP-Supply line flush3/12/20093/12/20093/12/2009PPART
DetailsForrest France
Forward flow testing of the backflow preventer completed satisfactory.
INSP-Sprinkler Rough-in/Hydro3/11/20093/11/20093/11/2009PPART
DetailsForrest France
Rough-in corrections noted, discussed forward flow testing date 3/12 pm.
INSP-Supply line flush3/2/20093/3/20093/3/2009APART
DetailsForrest France
Underground fire supply line flush completed satisfactory.
INSP-Sprinkler Rough-in/Hydro3/2/20093/2/20093/2/2009PPART
DetailsForrest France
Overhead rough-in completed okay with the exception of two mixed response heads at the concealed canopy area to be replaced, missing expansion tank for the antifreeze system, some items at the riser are not yet finished.
INSP-Sprinkler Rough-in/Hydro2/27/20093/2/20093/2/2009APART
DetailsForrest France
Both the underground supply pipe and overhead wet and antifreeze systems passed hydrostatic testing.
INSP-Supply line flush2/17/20092/18/20092/18/2009PPART
DetailsForrest France
UG fire supply line approved for bury including ductile riser.