Permit Information
Permit NumberFIR09-00133
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 234 S WHISPERWOOD
Project NameMEP GROUP LLC
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of a wet and dry system in a new building. There is one floor, a mezzanine and attic. The first floor wall studs protrude above the ceiling requiring fire protection above and below the ceiling.

A portion of the first floor will have shell protection ONLY. A separate permit will be required for the TI at a later date.

The building permit is BLD08-01796 and BLD08-01797 however the software will only allow attachment to a single building permit number.

The MEP Group Office Tenant Improvement - To finish a new 8,750 square foot, one story with 1,445 square foot mezzanine office tenant improvement. The mezzanine floor level to be used for mechanical and electrical storage only. This building is fully fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/28/20095/29/20095/29/2009APASS
DetailsForrest France
Verified a listed air maintenance device has been installed, fire sprinkler permit approved for final.
INSP-Final Inspection5/28/20095/28/20095/28/2009PFAIL
DetailsTroy Cobbley
Travis Phone #: ###-#### The air compressor/air maintenance device had not been resolved.
INSP-Final Inspection5/26/20095/27/20095/27/2009AFAIL
DetailsTroy Cobbley
As per my discussion with Tim Frost and Greg Patrick the dry system needs to have the air maintenance device installed as per approved drawing note 15 and 18. The air compressor exceeded the 30 pump up time but Jeremy was going to drop the air pressure down 2 or 3 pounds so that the 30 minute limitation is met. All other items including the fire alarm interconnection is complete.
INSP-Final Inspection5/22/20095/26/20095/26/2009AFAIL
DetailsTroy Cobbley
The forward flush passed but the interconnections with the fire alarm panel could not be tested due to problems with the facp.
INSP-Final Inspection5/22/20095/22/20095/22/2009PPART
DetailsForrest France
Final pending fire alarm system interconnections for riser supervision, trip testing, forward flow, final walkthrough, etc.
INSP-Sprinkler Rough-in/Hydro5/20/20095/20/20095/20/2009PPASS
DetailsTroy Cobbley
The hydro tests for the wet and dry systems passed. The sprinkler piping above the tile ceilings can be covered.
INSP-Sprinkler Rough-in4/15/20094/15/20094/15/2009PPASS
DetailsTroy Cobbley
The remaining piping rough-in for the west end is passed. The blocked upright and the missing upright previously noted have been corrected. A separate rough-in inspection will be required when the drops in the lay-in ceiling areas have been finished.
INSP-Sprinkler Rough-in4/9/20094/9/20094/9/2009PPART
DetailsTroy Cobbley
Todays inspection was for cover under the stairs, which it can be, but brian and I also did a rough-in on the wet system. I found one upright sprinkler head that needs to be relocated away from a 2x4 and one upright that needs to be added as shown on the plans. Also not all heads and lines were installed. These items will be checked when the hydro tests are called in.
INSP-Sprinkler Rough-in3/18/20093/19/20093/19/2009APASS
DetailsTroy Cobbley
24 hour air test for the overhead dry system passed.
INSP-Sprinkler Rough-in/Hydro3/18/20093/18/20093/18/2009PPASS
DetailsTroy Cobbley
The attic piping/rough-in passed and the piping can be covered.
INSP-Sprinkler Rough-in/Hydro3/18/20093/18/20093/18/2009APART
DetailsTroy Cobbley
The 24 hour air test was started at 9:15 with 42 1/2 psi on the guage.