INSP-Final Inspection | 7/14/2009 | 7/15/2009 | 7/15/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 7/5/2009 | 7/6/2009 | 7/6/2009 | P | PASS |
Troy Cobbley
|
|
|
overhead hydro bldg J passed.
|
INSP-Sprinkler Rough-in/Hydro | 6/18/2009 | 6/19/2009 | 6/19/2009 | P | PART |
Forrest France
|
|
|
Unit 514 Building J okayed for cover, noted missing SW head at the understair closet.
|
INSP-Sprinkler Rough-in | 6/4/2009 | 6/4/2009 | 6/4/2009 | A | PART |
Forrest France
|
|
|
See approved plans for 1st and 2nd floors okayed for cover in building J units 510 and 512.
|
INSP-Sprinkler Rough-in | 6/2/2009 | 6/3/2009 | 6/3/2009 | A | NH |
Forrest France
|
|
|
We respectfully request a partial rough-to-cover for Bld. J at the Iconic Apartments. Please call Scott 1 HOUR BEFORE inspection. **INSPECTORS NOTE**: Pease list contact phone number on inspection request. Niether approved set of sprinkler plans or contractor could be located on site, noted missing coverage at one location unit 512.
Thank you. Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2009 | 5/22/2009 | 5/25/2009 | A | FAIL |
Forrest France
|
|
|
UG supply line hydrostatic test failed due to pressure loss at the guage per inspection completed by T. Frost.
|
INSP-Sprinkler Rough-in | 5/19/2009 | 5/19/2009 | 5/19/2009 | P | PASS |
Troy Cobbley
|
|
|
The 2" underground supply piping is ok to cover. The contractor did not have the original approved plans, just copies, on site. I let him know those would be needed at the next inspection.
|