INSP-Final Inspection | 8/5/2009 | 8/7/2009 | 8/7/2009 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 8/5/2009 | 8/7/2009 | 8/7/2009 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 8/7/2009 | 8/7/2009 | 8/7/2009 | P | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 7/15/2009 | 7/16/2009 | 7/16/2009 | A | PART |
Troy Cobbley
|
|
|
Rough to cover apartment 502 is passed after the pendants in the upstairs apartment were spaced correctly. The problem is the repair work is leaking so the hydro test failed and will need to be rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 7/15/2009 | 7/15/2009 | 7/15/2009 | A | CANC |
Troy Cobbley
|
|
|
duplicate inspection
|
INSP-Sprinkler Rough-in/Hydro | 7/14/2009 | 7/14/2009 | 7/15/2009 | P | FAIL |
Troy Cobbley
|
|
|
above ground hydro failed. No rough in inspection was performed
|
INSP-Supply line flush | 6/5/2009 | 6/8/2009 | 6/8/2009 | P | PART |
Forrest France
|
|
|
UG fire supply line flushing completed okay.
|
INSP-Sprinkler Rough-in | 6/4/2009 | 6/4/2009 | 6/4/2009 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic retest passed.
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2009 | 5/22/2009 | 5/25/2009 | A | FAIL |
Forrest France
|
|
|
UG supply line hydrostatic test failed due to pressure loss at the guage per inspection completed by T. Frost.
|
INSP-Sprinkler Rough-in | 5/18/2009 | 5/19/2009 | 5/19/2009 | A | PASS |
Troy Cobbley
|
|
|
The 2" underground supply piping is ok to cover. The contractor did not have the original approved plans, just copies, on site. I let him know those would be needed at the next inspection.
|