INSP-Final Inspection | 7/14/2009 | 7/15/2009 | 7/15/2009 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 6/11/2009 | 6/12/2009 | 6/12/2009 | A | PART |
Troy Cobbley
|
|
|
Rough-to-cover inspection for building 504 is passed. A hanger was installed as I waited and metal flashing was cut away from the vertical riser as well.
|
INSP-Sprinkler Rough-in | 6/11/2009 | 6/11/2009 | 6/11/2009 | P | PART |
Forrest France
|
|
|
Building N unit 508 rough-in okayed, noted tie-in to the next unit at the 1st floor is not complete.
|
INSP-Supply line flush | 6/5/2009 | 6/8/2009 | 6/8/2009 | P | PART |
Forrest France
|
|
|
UG fire supply line flushing completed satisfactory. Note, see FIR09-00255 permit activities for UG cover inspection completed for this permit also.
|
INSP-Sprinkler Rough-in | 6/4/2009 | 6/4/2009 | 6/4/2009 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic retest passed.
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2009 | 5/22/2009 | 5/25/2009 | A | FAIL |
Forrest France
|
|
|
UG supply line hydrostatic test failed due to pressure loss at the guage per inspection completed by T. Frost.
|