Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR09-00261
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 2390 E FREIGHT ST
Project NameWinco Distribution Center
Customer Number 
ePlanReview 
Description
(Truck Return) The Fire Sprinkler Scope of work consists of a new wet pipe sprinkler system in a new building supplied from a city water main. The system utilizes large drop and regular sprinklers. A portion of the build (between grid lines H-P and 2-8) contains idle pallet storage of 20' high in a 30' high building utilizing a grid layout and large drop sprinklers. Fifteen heads were calculated. Portions of this area will be used to store Group A Plastics Exposed Unexpanded and expanded stored palletized, bin box, shelf, and rack to a maximum storage height of less than 5'-0" based on Ordinary Hazard Group II. The remainder of the building will be used for cleaning out trucks and a truck wash. The protection for this portion of the building is based on extra hazard group 1. There shall be no combustible or flammable liquids in the extra hazard group 1 portion of this build per NFPA 13: 5.4.1.

Truck Return Center - To construct a new 28,350 square foot, one story, pre-engineered metal building and related site improvements. This Truck Return Center building contains a 17, 900 sq. ft. warehouse area with small office and restroom, a 6,700 sq. ft. truck cleanout warehouse and a 3,750 sq. ft. truck wash and equipment areas. All construction per the approved plans and attached comment list. DRH07-00594 JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/24/200911/24/200911/27/2009APASS
DetailsForrest France
Corrections completed, fire sprinkler permit finaled.
INSP-Final Inspection9/15/20099/16/20099/17/2009APART
DetailsForrest France
TOC approved.
INSP-Final Inspection9/11/20099/11/20099/15/2009PPART
DetailsForrest France
Jeff Phone#: ###-####
INSP-Sprinkler Rough-in/Hydro9/3/20099/3/20099/4/2009PPART
DetailsForrest France
Overhead hydrostatic testing passed. Overhead rough-in inspection completed satisfactory, items incomplete include sprinklers under overhead doors at the wash bay and pressure relief valve at the riser.
INSP-Sprinkler Rough-in/Hydro9/2/20099/2/20099/2/2009PPART
DetailsForrest France
jeff Phone #: ###-####
INSP-Sprinkler Rough-in8/18/20098/19/20098/20/2009APART
DetailsForrest France
See approved plan set for red line annotations marked with today's date at two rooms including the restroom and electrical rooms okayed for ceiling cover.
FIR-Aging Inspection7/30/20097/30/20097/30/2009 DONE
DetailsForrest France
Work in progress, site construction underway.