INSP-Final Inspection | 8/4/2009 | 8/4/2009 | 8/4/2009 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit work okayed for final.
|
INSP-Sprinkler Rough-in/Hydro | 8/4/2009 | 8/4/2009 | 8/4/2009 | P | PASS |
Forrest France
|
|
|
C/N item and the overhead system hydrostatic test completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 7/31/2009 | 7/31/2009 | 7/31/2009 | P | FAIL |
Forrest France
|
|
|
One pendent head at the first floor hallway is overspaced, some heads remain yet to be replaced, remainder of permit work is acceptable, will need to schedule hydrostatic testing as discussed.
|