INSP-Final Inspection | 7/15/2010 | 7/15/2010 | 7/15/2010 | P | PASS |
Forrest France
|
|
|
Acceptance testing and final inspections passed. Permit final approved.
|
INSP-Final Inspection | 7/6/2010 | 7/8/2010 | 7/6/2010 | P | CANC |
Forrest France
|
|
|
Final insprction and forward flow the backflow.
Call Kerry ###-#### can we do 1:00pm Inspection requested from web by: Brad Bettencourt Phone #: ###-#### Inspection cancelled from web by: Brad Bettencourt
|
INSP-Sprinkler Rough-in | 3/1/2010 | 3/1/2010 | 3/2/2010 | P | PART |
Forrest France
|
|
|
Regarding overhead work for FIR09-00536.
|
INSP-Sprinkler Rough-in/Hydro | 2/5/2010 | 2/8/2010 | 2/8/2010 | A | PART |
Forrest France
|
|
|
On site inspection to verify insulation fill at the concealed space above the library- Okay to cover.
|
INSP-Conference | 11/30/2009 | 12/1/2009 | 12/1/2009 | A | DONE |
Forrest France
|
|
|
Conference regarding project related fire sprinkler work at the gym, new window soffits, and seismic bracing attatchments.
|
INSP-Conference | 11/30/2009 | 11/30/2009 | 11/30/2009 | P | CANC |
Troy Cobbley
|
|
|
Per phone conversation with Rob, this inspection will be rescheduled for tomorrow morning.
|
INSP-Conference | 9/24/2009 | 9/25/2009 | 9/25/2009 | A | DONE |
Forrest France
|
|
|
Regarding concealed spaces and NFPA 13 sec. 8.15.
|
INSP-Conference | 9/17/2009 | 9/17/2009 | 9/17/2009 | P | DONE |
Forrest France
|
|
|
On site conference regarding overhead permit work. Discussed NFPA 13 2007 sec. 8.15.7.1.
|
INSP-Supply line flush | 8/18/2009 | 8/20/2009 | 8/20/2009 | A | PASS |
Troy Cobbley
|
|
|
The underground supply hydro test and flush passed inspection. Also mark sentenno has approved the location of the PIV.
|
INSP-Supply line flush | 8/18/2009 | 8/19/2009 | 8/19/2009 | P | PASS |
Troy Cobbley
|
|
|
The underground supply piping can be covered. Final approval of the PIV location will need to be approved by mark sentenno since it is less than 40' from the building and is not located as shown on the plans. Also the two 45 degree fittings shown on the city approved plans did not need to be installed and the underground was installed straight into the building. Also the "deadman" fittings could not be inspected since several yards of concrete have already been poured over them. None of the interior penatration of the underground supply has been inspected.
|
INSP-Conference | 8/17/2009 | 8/18/2009 | 8/18/2009 | A | DONE |
Forrest France
|
|
|
On site visit regarding underground fire supply line depth of bury and PIV location. Minimum cover of 4' 6" from finish grade to the top of pipe to be maintained per BMC amendments and NFPA 13 guidelines.
|