This fire alarm permit is to provide a new fire alarm system for sprinkler system monitoring, duct detectors for HVAC, and monitoring for a special releasing system in a computer room. Notification devices are not part of this permit scope.

Associated building permit: BLD09-01062 (AMALGAMATED SUGAR COMPANY) Remodel for a 23,116 sq. ft. tenant in an existing building to include demolition of existing office areas and construction of new office layout. Existing lay-in ceiling to remain where possible, new interior finishes where required with minor exterior storefront work per approved plans. Work to include: construction of interior partitions creating; individual office areas, open office area, small conference rooms, computer room, board room, training room, storage area, break room, and reception areas. Installation of a suspended ceiling system, installation of new HVAC unit, miscellaneous related interior finishes, fire sprinkler work, new mechanical, new plumbing, and new electrical work. A Certificate of Occupancy is to be issued when completed and approved. NOTE: This building is fully fire sprinklered for area increase, any alterations or modifications to the sprinkler system shall be per NFPA #13 as regulated by the fire department. CZC09-00127 **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/23/20099/23/20099/23/2009PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Alarm Testing8/26/20098/26/20098/26/2009PPART
DetailsTroy Cobbley
A temporary occupancy was given with scott and marks approval. An updated map needs to be provided at the facp as discussed that shows the actual number and location of the duct smoke detectors.
INSP-Final Inspection8/25/20098/25/20098/25/2009PFAIL
DetailsTroy Cobbley
None of the items tested passed due to the monitoring station not receiving the correct signals. All of the items tested today will need to be retested. Also several of the hvac units/duct smoke detectors could not be tested due to the gas meter being locked. Also Allied General was not complete with the releasing system that is interconnected with this new panel.
INSP-Sprinkler Rough-in8/18/20098/19/20098/19/2009APART
DetailsTroy Cobbley