INSP-Final Inspection | 11/19/2009 | 11/20/2009 | 11/20/2009 | A | PASS |
Forrest France
|
|
|
Correction items field verified for compliance, final walkthrough passed, permit finaled.
|
INSP-Final Inspection | 11/17/2009 | 11/18/2009 | 11/18/2009 | A | NR |
Forrest France
|
|
|
Final pending the installation of three missing tamper switches at the main control valves for the fire service water supply per IFC 903.4 and permit work fire code review note #10.
|
INSP-Final Inspection | 11/17/2009 | 11/17/2009 | 11/17/2009 | P | PART |
Forrest France
|
|
|
Items needed for final include head guards at sprinklers in low ceilings, signage at the antifreeze riser, state fire marshal tags, open the valve to the expansion tank, obstructed head at one closet, all valves controlling the water supply to the fire sprinkler system shall be electrically supervised per IFC 2006 sec. 903.4- see fire code review note #10.
|
INSP-Sprinkler Rough-in | 10/27/2009 | 10/27/2009 | 10/27/2009 | P | PART |
Forrest France
|
|
|
Overhead rough-in inspection for the 2nd floor antifreeze system okayed for cover, discussed items remaining for permit final.
|
INSP-Sprinkler Rough-in/Hydro | 10/26/2009 | 10/27/2009 | 10/27/2009 | A | PART |
Forrest France
|
|
|
2nd floor antifreeze system hydrostatic testing completed acceptable, inspection passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/19/2009 | 10/19/2009 | 10/19/2009 | A | PART |
Forrest France
|
|
|
Okay to cover 1st floor as noted on stamped plan set.
|
INSP-Supply line flush | 10/5/2009 | 10/6/2009 | 10/6/2009 | A | PART |
Forrest France
|
|
|
Underground fire supply line flush completed satisfactory.
|
INSP-Supply line flush | 10/2/2009 | 10/5/2009 | 10/5/2009 | A | CANC |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 10/2/2009 at 9:45:50 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Oct 5 2009 7:17AM.
|
INSP-Sprinkler Rough-in/Hydro | 10/1/2009 | 10/2/2009 | 10/2/2009 | A | PART |
Forrest France
|
|
|
1st floor overhead rough-in inspection is acceptable, minor field mods. okayed, noted one flexible coupling to be added at the feed to the second floor system. Overhead hydrostatic test of the 1st floor also passed.
|
INSP-Supply line flush | 10/1/2009 | 10/2/2009 | 10/2/2009 | A | NR |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 10/1/2009 at 2:35:17 PM. Contact: ###-####.
|
INSP-Conference | 9/23/2009 | 9/24/2009 | 9/24/2009 | A | PART |
Forrest France
|
|
|
Inspection intended for an underground fire supply line cover, okayed for bury as discussed.
|
INSP-Conference | 9/22/2009 | 9/23/2009 | 9/23/2009 | A | DONE |
Forrest France
|
|
|
Regarding fire supply line depth of cover.
|