Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR09-00478
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 1072 N LIBERTY ST
Project NameMulvaney MOB
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of adding and relocating sprinklers in two separate areas on two floors to accommodate new wall and ceiling configurations. The existing system is a 3"x2 ½"x 1 ½" grid.

(MULVANEY M.O.B. - 2nd & 3rd Floor Lobbies - Shell & Core Upgrade) Permit is to build out the second and third floor lobbies of the shell permit (BLD08-01210). Approval contingent on adhering to approved plans. Work to include: construction of interior non-bearing walls to define the second and third floor lobbies, installation of new lighting, new hi/low drinking fountains (one on each floor), new mechanical system, new doors and hardware, and interior finishes in compliance with chapter 8 of the 2006 IBC. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. This permit does not allow occupancy, future permits will be required to occupy any portion of this building. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/16/20099/16/20099/17/2009PPASS
DetailsForrest France
Fire sprinkler permit work approved for final status, inspection passed.
INSP-Sprinkler Rough-in/Hydro9/9/20099/9/20099/9/2009PPART
DetailsForrest France
See annotations on approved plans for overhead work at the 2nd and 3rd floor drop and sheetrock ceilings okayed for cover.