INSP-Final Inspection | 9/23/2009 | 9/24/2009 | 9/24/2009 | A | PASS |
Forrest France
|
|
|
Remainder of permit work passed inspection, fire sprinkler permit finaled.
|
INSP-Final Inspection | 9/14/2009 | 9/14/2009 | 9/14/2009 | A | PART |
Forrest France
|
|
|
New coolers and dry pendent heads not yet installed, remainder of work okayed.
|
INSP-Sprinkler Rough-in | 9/4/2009 | 9/4/2009 | 9/4/2009 | A | PART |
Forrest France
|
|
|
Fire sprinkler work completed to date is acceptable, dry pendent heads at the new freezers are not yet installed.
|
INSP-Final Inspection | 9/2/2009 | 9/3/2009 | 9/3/2009 | A | CANC |
Forrest France
|
|
|
Overbooked
|
INSP-Sprinkler Rough-in | 8/31/2009 | 8/31/2009 | 8/31/2009 | P | PART |
Troy Cobbley
|
|
|
I gave the ok to cover in the two small pockets where the coolers go. There is alot of combustibles above the ceiling in the bakery area and a mechanical mezzanine above as well. There is partial upright coverage but not complete coverage.
|
INSP-Sprinkler Rough-in | 8/28/2009 | 8/31/2009 | 8/31/2009 | A | PART |
Troy Cobbley
|
|
|
I gave the ok to cover in the two small pockets where the coolers go. There is alot of combustibles above the ceiling in the bakery area and a mechanical mezzanine above as well. There is partial upright coverage but not complete coverage.
|
INSP-Sprinkler Rough-in | 8/28/2009 | 8/28/2009 | 8/28/2009 | P | DEFR |
Forrest France
|
|
|
Overbooked, to be rescheduled as discussed.
|
INSP-Sprinkler Rough-in | 8/27/2009 | 8/27/2009 | 8/28/2009 | P | NR |
Forrest France
|
|
|
Per site visit by T. Frost dated 8/27/09, work is incomplete and not ready for inspection as requested.
|