INSP-Final Inspection | 7/13/2010 | 7/15/2010 | 7/15/2010 | A | PASS |
Forrest France
|
|
|
Final acceptance testing and inspection passed. See also project related FIR09-00449 for activity notes regarding this permit. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 7/6/2010 | 7/8/2010 | 7/8/2010 | P | NR |
Forrest France
|
|
|
Not ready per conversation with contractor.
|
INSP-Conference | 7/7/2010 | 7/7/2010 | 7/7/2010 | A | DONE |
Forrest France
|
|
|
Regarding project completion, coordination with alarm work, and final inspection schedule.
|
INSP-Sprinkler Rough-in/Hydro | 6/7/2010 | 6/7/2010 | 6/7/2010 | P | PART |
Forrest France
|
|
|
Hydrostatic testing for the first floor and basement level systems passed.
|
INSP-Sprinkler Rough-in/Hydro | 6/4/2010 | 6/7/2010 | 6/7/2010 | P | PART |
Forrest France
|
|
|
Overhead rough-in at the basement and 1st floor levels approved for cover. Discussed items remaining for final.
|
INSP-Sprinkler Rough-in | 6/4/2010 | 6/7/2010 | 6/4/2010 | A | CANC |
Forrest France
|
|
|
Basement Rough-In Kerry is the person to contact. Would tike to have this First thing in the morning. 8:00 am if possable. Inspection requested from web by: Brad Bettencourt Phone #: ###-#### Inspection cancelled from web by: Brad Bettencourt
|
INSP-Sprinkler Rough-in | 6/2/2010 | 6/4/2010 | 6/4/2010 | P | CANC |
Troy Cobbley
|
|
|
rOUGH-IN IN THE BASEMENT Inspection requested from web by: Brad Bettencourt Phone #: ###-#### Inspection cancelled from web by: Brad Bettencourt
|
INSP-Sprinkler Rough-in/Hydro | 6/2/2010 | 6/4/2010 | 6/4/2010 | P | CANC |
Troy Cobbley
|
|
|
200LB for the 1st floor system.Bard Inspection requested from web by: Brad Bettencourt Phone #: ###-#### Inspection cancelled from web by: Brad Bettencourt
|
INSP-Sprinkler Rough-in/Hydro | 6/2/2010 | 6/3/2010 | 6/2/2010 | P | CANC |
Forrest France
|
|
|
200 LB for the 1st floor system. Brad Inspection requested from web by: Brad Bettencourt Phone #: ###-#### Inspection cancelled from web by: Brad Bettencourt
|
INSP-Sprinkler Rough-in | 5/17/2010 | 5/18/2010 | 5/18/2010 | A | PART |
Forrest France
|
|
|
Overhead install at the first floor approved for cover per annotations on stamped plan set marked with today's date with the exception of stair 127 not yet finished. Also noted head guards to be provided for upright heads at the gym.
|
INSP-Sprinkler Rough-in | 5/14/2010 | 5/17/2010 | 5/17/2010 | P | CANC |
Troy Cobbley
|
|
|
I spoke to todd and they were leaving the job site and I was not going to make it do to time constraints.. Todd said he would reschedule for tommorrow
|
INSP-Sprinkler Rough-in | 4/21/2010 | 4/22/2010 | 4/22/2010 | A | PART |
Forrest France
|
|
|
The remainder of overhead rough-in at the second floor drop ceilings is approved for cover including the main corridor and perimeter rooms. Verified fire resistive coatings at exposed wood above the ceiling grid, noted ball valve at one drop sprinkler head to be removed at the north end of the corridor.
|
INSP-Sprinkler Rough-in/Hydro | 3/29/2010 | 3/29/2010 | 3/29/2010 | P | PART |
Forrest France
|
|
|
Todd Phone #: 941- 6014
|
INSP-Sprinkler Rough-in | 3/26/2010 | 3/26/2010 | 3/26/2010 | P | PART |
Forrest France
|
|
|
See clouded areas marked on stamped plan set at the second floor level classrooms okayed for ceiling cover- Includes rough-in and final head locations. Classroom 202 at the south end is not approved for cover due to exposed combustible construction above the drop ceiling lacking protection. Seismic brace locations at the feed mains in the basement riser room are acceptable.
|
INSP-Sprinkler Rough-in | 3/2/2010 | 3/2/2010 | 3/2/2010 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test for the new dry system at the attic passed inspection.
|
INSP-Sprinkler Rough-in/Hydro | 2/25/2010 | 2/26/2010 | 2/26/2010 | A | PART |
Forrest France
|
|
|
Concluded satisfactory 24 hr. air testing of the new dry system.
|
INSP-Sprinkler Rough-in | 2/24/2010 | 2/25/2010 | 2/25/2010 | A | PART |
Forrest France
|
|
|
Begin 24 hr. pneumatic testing of the new dry system at 11:00PM @41psig.
|
INSP-Sprinkler Rough-in | 2/16/2010 | 2/16/2010 | 2/17/2010 | P | NR |
Forrest France
|
|
|
For overhead work at second floor stairways.
|
INSP-Sprinkler Rough-in | 2/11/2010 | 2/12/2010 | 2/12/2010 | A | PART |
Forrest France
|
|
|
Rough-in inspection for the attic dry system completed satisfactory, main tie-ins are not yet finished, discussed seismic bracing, overhead piping at second floor stairways, insulation fill at the main entry vestibule okayed.
|
INSP-Sprinkler Rough-in | 2/11/2010 | 2/11/2010 | 2/11/2010 | P | CANC |
Troy Cobbley
|
|
|
Cancelled due to time constraints and Micron plan review. I spoke to todd and the inspection will be rescheduled for tomorrow.
|
INSP-Sprinkler Rough-in | 2/1/2010 | 2/2/2010 | 2/2/2010 | P | PART |
Forrest France
|
|
|
Tenting for cold cavity protection of wet system piping at the library room is satisfactory. Discussed inspection schedule for insulation fill at this area to meet NFPA 13 exceptions.
|
INSP-Sprinkler Rough-in | 1/21/2010 | 1/21/2010 | 1/21/2010 | P | PART |
Forrest France
|
|
|
Overhead fire sprinkler installation at the library room 128 is acceptable. Cover okay pending satisfactory tenting for cold cavity protection. Also need to verify non-combustible insulation fill to meet the exception allowed for non-sprinklered concealed spaces per NFPA 13 as the uprights in this area per plans have been deleted.
|
INSP-Conference | 1/14/2010 | 1/14/2010 | 1/14/2010 | P | DONE |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 1/7/2010 | 1/8/2010 | 1/8/2010 | A | PART |
Forrest France
|
|
|
Okay to cover remainder of sheetrock lid ceiling areas as marked on the approved plan set with today's date and initials.
|
INSP-Sprinkler Rough-in | 1/5/2010 | 1/7/2010 | 1/7/2010 | A | FAIL |
Forrest France
|
|
|
Upright heads at three closets on the first floor are too far below the deck, two mech. shafts and one custodial closet are not yet piped. Remainder of sheetrock lids at the first and second floors are okay for cover- see annotations on plans with today's date for locations.
|
INSP-Conference | 12/8/2009 | 12/8/2009 | 12/9/2009 | P | DONE |
Forrest France
|
|
|
Discussion regarding product listings for fire resistant coatings.
|
INSP-Conference | 11/4/2009 | 11/4/2009 | 11/4/2009 | A | DONE |
Forrest France
|
|
|
Regarding sprinkler coverage at the main entry exterior canopy.
|
INSP-Conference | 10/5/2009 | 10/6/2009 | 10/6/2009 | P | DONE |
Forrest France
|
|
|
On site conference regarding fire sprinkler coverage at the concealed space above the library room.
|