INSP-Final Inspection | 5/6/2010 | 5/7/2010 | 5/7/2010 | A | PASS |
Forrest France
|
|
|
Overhead fire sprinkler permit finaled, final walkthrough passed.
|
INSP-Final Inspection | 4/30/2010 | 5/3/2010 | 5/3/2010 | A | PART |
Forrest France
|
|
|
See plan review comments regarding control valve operations at post indicators or provision for a one hour rated riser room. Forward flow completed satisfactory.
|
INSP-Final Inspection | 4/27/2010 | 4/28/2010 | 4/28/2010 | A | PEND |
Forrest France
|
|
|
jon Phone #: ###-#### ref. activity note 4/27
|
INSP-Final Inspection | 4/26/2010 | 4/27/2010 | 4/27/2010 | A | DEFR |
Forrest France
|
|
|
Pending project related fire alarm permit FIR10-00057- no field inspection request by contractor on this permit to date. Fire alarm work must pass functional testing and final approval in sequence with sprinkler final.
|
INSP-Final Inspection | 4/19/2010 | 4/20/2010 | 4/20/2010 | A | NR |
Forrest France
|
|
|
Final pending project related fire alarm permit.
|
INSP-Sprinkler Rough-in/Hydro | 3/25/2010 | 3/26/2010 | 3/26/2010 | A | PART |
Forrest France
|
|
|
Remote FDC piping hydrostatic test completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 3/25/2010 | 3/25/2010 | 3/25/2010 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic testing for both the wet and antifreeze systems passed.
|
INSP-Sprinkler Rough-in | 3/8/2010 | 3/8/2010 | 3/12/2010 | A | PART |
Forrest France
|
|
|
Jonathan Phone #: ###-#### Re: access at riser room
|
INSP-Sprinkler Rough-in | 3/3/2010 | 3/5/2010 | 3/5/2010 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler work at the grid ceilings throughout are approved for cover.
|
INSP-Conference | 1/11/2010 | 1/12/2010 | 1/12/2010 | A | DONE |
Forrest France
|
|
|
Jonathan Phone #: ###-#### Re: antifreeze system testing
|
INSP-Sprinkler Rough-in/Hydro | 1/7/2010 | 1/7/2010 | 1/7/2010 | P | NR |
Forrest France
|
|
|
Overhead not ready for hydrostatic test.
|
INSP-Sprinkler Rough-in/Hydro | 12/7/2009 | 12/7/2009 | 12/7/2009 | A | PART |
Forrest France
|
|
|
Overhead modifications to the antifreeze system at the exterior canopies are okay for cover. Not ready for hydrostatic testing at this time.
|
INSP-Sprinkler Rough-in | 12/3/2009 | 12/3/2009 | 12/3/2009 | A | PART |
Forrest France
|
|
|
Verified added upright protection at the first floor canopies, overhead installation at both the first and second floors okay for cover.
|
INSP-Sprinkler Rough-in | 12/2/2009 | 12/2/2009 | 12/2/2009 | P | PART |
Forrest France
|
|
|
Overhead rough-in at the first and second floors both wet and antifreeze systems inspected today, items noted include coverage at canopies per NFPA 13 sec. 8.15.7, minor field mods at upright head coverage in two rooms, seismic attatchments in wood members per ch. 9 NFPA. Riser is not yet built.
|
INSP-Sprinkler Rough-in | 11/4/2009 | 11/4/2009 | 11/4/2009 | P | NH |
Forrest France
|
|
|
|