Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR09-00561
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 960 S BROADWAY AVE Unit: 500
Project NamePETROGLYPH ENERGY
Customer Number 
ePlanReview 
Description
Quick Permit
Change out all sprinklers on the fifth floor to quick response.
(PETROGLYPH ENERGY) (SUITE 500) This building is required to be fully fire sprinklered. To create a 10,185 square foot office tenant space from a larger space located on the 5th story. Work is to include a toilet room accessible to the disabled, a shower room accessible to the disabled, interior nonbearing walls, interior windows, interior doors, millwork, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. If the existing automatic sprinklers within this tenant space are not quick-response, they are required to be replaced with quick-response automatic sprinklers. The adjacent tenant space is not allowed to be occupied under this permit. The tenant who intends to occupy the adjacent tenant space is required to get its own Certificate of Occupancy before occupying that space. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/29/200910/30/200910/30/2009APASS
DetailsForrest France
Final walkthrough of permit work passed, fire sprinkler finaled.
INSP-Sprinkler Rough-in/Hydro10/19/200910/19/200910/19/2009APART
DetailsForrest France
Work in progress
INSP-Sprinkler Rough-in/Hydro10/15/200910/16/200910/16/2009APASS
DetailsTroy Cobbley
The 5th floor hydro test passed.
INSP-Sprinkler Rough-in/Hydro10/12/200910/13/200910/13/2009ACANC
DetailsTroy Cobbley
Cancelled per phone conversation with Tom. As a side note I was performing a fire alarm test in the building and found that the guage dropped from 203 to 198 over a couple hour period.
INSP-Sprinkler Rough-in/Hydro10/9/200910/12/200910/12/2009AFAIL
DetailsTroy Cobbley
Todays inspection was for the overhead hydro test which failed.
INSP-Sprinkler Rough-in9/28/20099/29/20099/29/2009ANR
DetailsForrest France
Inspection intended for project related tenant improvement permit FIR09-00413.