INSP-Final Inspection | 4/26/2010 | 4/27/2010 | 4/27/2010 | A | PASS |
Forrest France
|
|
|
Scope of fire sprinkler work passed final walkthrough, noted corrections finished, inspection passed.
|
INSP-Conference | 2/25/2010 | 2/26/2010 | 2/26/2010 | A | DONE |
Forrest France
|
|
|
On site visit with responding fire department station 12 crew and Captain Bill Ream regarding insufficient access to the existing FDC due to adjacent building service equipment and surrounding fenced enclosure. Fire department connections must be in compliance with IFC 2006 sec. 912.1, 912.2, 912.3 for installation, location and access. Contractor to provide plan modification documents indicating proposed new FDC location in accordance with the applicable standards prior to site inspection for approval. Power Bar representatives Michael Fanelle and Michelle McMullen included in the discussion on premise. Permit finals pending.
|
INSP-Conference | 2/24/2010 | 2/25/2010 | 2/26/2010 | A | DONE |
Forrest France
|
|
|
Site visit scheduled 2/26 @ 9:30AM.
|