Permit Information
Permit NumberFIR10-00032
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 1055 N CURTIS RD
Project NameST ALPHONSUS
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of adding and relocating sprinklers to accommodate new wall and ceiling configuration.

(ST ALPHONSUS - CLINICAL LABORATORY RENOVATION) Renovation of existing Clinical Laboratory Department to accommodate the installation of an automatic testing line and relocation of the Histology and Cytology Departments. Work will include selective interior demolition in five different phases in conjunction with five phases of tenant remodel to allow Lab functions to continue. In order to maintain operation requirements of the Lab some existing rooms in the immediate Lab Clinic area will receive minimum modifications to facility maintaining use of equipment and work stations for lab activities while their portion of the clinic is demolished and remodeled. At the conclusion of the remodel all activities and support functions will be within the existing Clinical Lab and expanded Histology and Cytology Departments in the SE corner of the 1st floor of SARMC. Work includes construction of new non-bearing walls to create work / testing areas, relocation of existing walk-in cooler; relocation / construction of existing 2-hour fire barrier wall on west and north sides of new Cytology Dept.; structural modification for new door opening in concrete wall between Histology 101 & Cytology 103 (see 8-1/2" xx 11" structural design and details); and upgrades of electrical, mechanical, plumbing, sprinkler and alarm systems to meet tenant needs and provide / maintain code compliance. Drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/8/201012/8/201012/8/2010PPASS
DetailsTroy Cobbley
permit finaled
FIR-Aging Inspection11/23/201011/23/201011/30/2010 NR
DetailsTroy Cobbley
work is in progress
INSP-Sprinkler Rough-in11/29/201011/29/201011/29/2010PPASS
DetailsTroy Cobbley
See the city approved plans for the office where the sprinkler piping can be covered.
INSP-Sprinkler Rough-in9/1/20109/1/20109/1/2010PPASS
DetailsTroy Cobbley
See the city approved plans for locations were the sprinkler piping can be covered. It will have todays date.
INSP-Sprinkler Rough-in7/14/20107/14/20107/14/2010PPASS
DetailsTroy Cobbley
The sprinkler piping in phase 3B is ok to cover. See the city approved plans marked with todays date for specific area.
INSP-Final Inspection5/18/20105/18/20105/18/2010PPASS
DetailsTroy Cobbley
The fire sprinkler work in phase two passed inspection
INSP-Sprinkler Rough-in5/11/20105/12/20105/12/2010APASS
DetailsTroy Cobbley
The phase 2 sprinkler piping is ok to cover.
INSP-Final Inspection4/8/20104/8/20104/8/2010PPART
DetailsTroy Cobbley
The phase 1 fire sprinkler work is passed.
INSP-Sprinkler Rough-in3/19/20103/22/20103/22/2010APASS
DetailsTroy Cobbley
The phase 1 sprinkler piping, as marked and dated on the plans, is ok to cover.