Permit Information
Permit NumberFIR10-00047
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 9180 W BARNES DR
Project NameJaguar Plaza
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of adding and relocating sprinklers to accommodate new wall and ceiling configuration. The area in this permit is the south portion of the building. The existing sprinkler system appears to be a 3"x2"x1½" compound grid.

(NCO FINANCIAL SYSTEMS, Inc. - Jaguar Plaza) Permit is to modify an existing 5,910 square foot tenant space to become two tenant spaces, NCO Financial will occupy the south east 3,309 square feet of this building. Approval contingent upon adhering to the approved plans on file. Work to include: [construction of interior non-bearing wall to create two separate tenant spaces, a break room, and a manager's office], installation of new hi / low drinking fountain, and finishes in compliance with chapter 8 of the 2006 IBC. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. Racking that exceeds 8 ft. in height requires a separate Building Permit be submitted and approved before installation. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/24/20103/24/20103/24/2010PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in3/18/20103/19/20103/19/2010AFAIL
DetailsForrest France
Jeremy Phone #: ###-####

Several upright sprinklers were painted and needed to be replaced.
Was unable to gain access to room 100 to verify the fire protection.
Room 103, the storage was to close to the sprinkler and obstructed the coverage. I notify a tenant representative of the obstruction problem.
INSP-Final Inspection2/24/20102/25/20102/25/2010APART
DetailsTroy Cobbley
phase one fire sprinkler work is complete
INSP-Sprinkler Rough-in2/18/20102/18/20102/18/2010PPASS
DetailsTroy Cobbley
Phase I sprinkler piping ok to cover.