INSP-Final Inspection | 12/29/2010 | 12/30/2010 | 12/30/2010 | A | PASS |
Forrest France
|
|
|
Correction items field verified. Final inspection passed. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 12/28/2010 | 12/29/2010 | 12/29/2010 | A | PART |
Forrest France
|
|
|
Added EC heads okayed and verified per resubmitals. Final walkthrough passed with the exception of three areas in need of revision including provide matched temp. heads at the second floor stairway, amend blocked coverage at the main entry lobby, add protection under a new raised equipment access deck at the attic space.
|
INSP-Conference | 12/3/2010 | 12/3/2010 | 12/3/2010 | P | DONE |
Forrest France
|
|
|
Regarding project schedule.
|
INSP-Sprinkler Rough-in/Hydro | 10/13/2010 | 10/14/2010 | 10/15/2010 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test of the new wet system completed satisfactory.
|
INSP-Supply line flush | 10/6/2010 | 10/7/2010 | 10/7/2010 | A | PART |
Forrest France
|
|
|
Underground fire supply line flushing completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 10/5/2010 | 10/5/2010 | 10/6/2010 | P | PASS |
Forrest France
|
|
|
Underground fire supply line hydrostatic test passed.
|
INSP-Sprinkler Rough-in | 9/2/2010 | 9/3/2010 | 9/3/2010 | A | PART |
Forrest France
|
|
|
See annotations marked on approved plans for locations of areas inspected today.
|