Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR10-00377
StatusFinaled
Name SIMPLEX GRINNELL
Site Address 101 S CAPITOL BLVD Unit: 1801
Project NameUS BANK Unit 1801
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of adding, removing and relocating sprinklers to accommodate new wall and ceiling configuration. According to the contractor there are (2) 750 Gpm @ 200 Psi fire pumps located in the basement. There are 6" standpipes, 3" feed main and a 2" loop. Change all sprinklers to quick response. When this permit is completed, the entire building will have been changed to quick response type sprinklers per the upgrade agreement of 06-19-03 as referenced in BLD03-00539.

________________________________________

Building Department Scope:

(US Bank Building - Ste#1801 - 18th Floor) PLAN MODIFICATION 7-22-10 - Modification submitted to reconfigure office and work stations layout. The reconfiguring of the space will also spark ceiling and lighting changes. **TLW** Permit is to remodel a 9,126 square foot portion of an existing office tenant space (Stole Rives - BLD04-00029. Approval contingent upon adhering to the approved plans on file and attached engineering. Work to include: construction of interior non-bearing walls to create multiple additional office use areas, a conference room (432 square feet), demo / infill existing open stairway, install spray on fire-proofing, installation of new plumbing, installation of new doors / hardware, relocating / removing existing lighting, and finishes in compliance with chapter 8 of the 2006 IBC. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. Racking that exceeds 8 ft. in height requires a separate Building Permit be submitted and approved before installation. PLAN MODIFICATION 7-22-10 - Modification submitted to reconfigure office and work stations layout. The reconfiguring of the space will also spark ceiling and lighting changes. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/8/20109/9/20109/9/2010APASS
DetailsForrest France
Fire sprinkler work passed final walkthrough, permit finaled.
INSP-Sprinkler Rough-in8/9/20108/9/20108/9/2010PPART
DetailsForrest France
Overhead fire sprinkler modifications per the scope of work are approved for cover at the drop ceilings.