Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberFIR10-00394
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 703 S AMERICANA BLVD Unit: 120
Project NameBoise Orthopedic Clinic
Customer Number 
ePlanReviewNo
Description
Ameriancan West Building
The Fire Sprinkler Scope of work consists of adding and relocating sprinklers to accommodate a new wall and ceiling layout. The existing system is reported as a grid, with 2 ½" primary main, 2" secondary mains and 1¼" branch lines. The existing water flow information is S-55, R-20, Q-3000, and D-07/2001.

________________________________________

Building Department Scope:

Permit is to remodel 6,300 square foot portion of an existing building. The 6,300 square feet is a combination of the remaining portions of BLD10-01138 and Pioneer Title & Escrow (BLD05-03033). Approval is contingent upon adhering to the approved plans on file. Work is to include: [construction of interior non-bearing walls to create separate sex accessible bathrooms, two unisex accessible bathrooms, 12 exam rooms, 4 offices, a reception / waiting area, a new vestibule, 5 storage rooms, a nurses station, and a wet clean room], installation of new plumbing, installation of new lighting, installation of new mechanical, installation of new doors / hardware, and finishes in compliance with chapter 8 of the 2006 IBC. This is a fully fire sprinklered building any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT. The system shall be installed per NFPA #13 as regulated by the fire department. Racking that exceeds 8 ft. in height requires a separate Building Permit. The permit shall be submitted and approved before installation. **TLW** --TRF--
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/2/201012/2/201012/3/2010PPASS
DetailsForrest France
Correction items field verified for completion, final walkthrough passed. Permit finaled.
INSP-Conference11/16/201011/16/201011/17/2010PDONE
DetailsForrest France
Regarding comm room ceiling for area separation.
INSP-Sprinkler Rough-in11/9/201011/10/201011/11/2010APART
DetailsForrest France
Items include provide area separation at the comm. room, noted three hangers in need of adjustment or relocation, provide matched response head at the skylight. Drop ceilings okay for cover.