INSP-Final Inspection | 4/4/2011 | 4/4/2011 | 4/4/2011 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 3/28/2011 | 3/29/2011 | 3/29/2011 | P | PASS |
Troy Cobbley
|
|
|
hydro for second floor passed.
|
INSP-Sprinkler Rough-in/Hydro | 3/23/2011 | 3/24/2011 | 3/24/2011 | A | PASS |
Forrest France
|
|
|
Passed hydro.
Steph Phone #: ###-####
|
INSP-Sprinkler Rough-in | 3/23/2011 | 3/23/2011 | 3/23/2011 | P | PASS |
Troy Cobbley
|
|
|
The under mezzanine sprinkler piping, showroom side of wall, is ok to cover.
|
INSP-Sprinkler Rough-in | 3/18/2011 | 3/22/2011 | 3/22/2011 | A | PASS |
Troy Cobbley
|
|
|
The Showroom area sprinkler piping is ok to cover. The pendant sprinkler heads have not been installed in the same locations shown on the approved plans but mathmatically the coverage appears to still be adequate.
|
INSP-Sprinkler Rough-in | 3/8/2011 | 3/9/2011 | 3/9/2011 | A | PASS |
Troy Cobbley
|
|
|
See the latest city approved plan modification for areas where the sprinkler piping can be covered. I pointed out that quick responce sprinklers are required in all light hazard areas.
|
INSP-Sprinkler Rough-in | 2/25/2011 | 2/28/2011 | 2/28/2011 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where piping is ok to cover. I re-iterated that resubmittals will be required and the possiblility of a stop work order if work that does not match the plans proceeds.
|
INSP-Sprinkler Rough-in | 2/22/2011 | 2/23/2011 | 2/23/2011 | A | PART |
Troy Cobbley
|
|
|
See the city approved plans for piping clouded in red that was inspected. The installation itself appears ok except plans need to be resubmitted showing the pipe routing changes on the gridded portion of the sprinkler system. Branchlines and mains have both been moved with additional fittings but in some instances fittings eliminated. Final locations of pendants have not been inspected yet.
|
INSP-Final Inspection | 12/15/2010 | 12/15/2010 | 12/15/2010 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Jennifer's permission until the existing building scope of work is complete. The scope of work in the new building is completed at this time except for the existing building riser.
|
INSP-Final Inspection | 12/13/2010 | 12/14/2010 | 12/14/2010 | A | FAIL |
Troy Cobbley
|
|
|
The forward flush passed inspection. Items remaining for a temporary occupancy in the service portion, include the testing of the fire alarm panel interconnection.
|
INSP-Final Inspection | 12/10/2010 | 12/13/2010 | 12/13/2010 | A | CANC |
Troy Cobbley
|
|
|
Rescheduled for tomorrow. Bill did not have the pito guage for the forward flow test and the fire alarm permit had not been called in for the testing of the fire alarm/fire sprinkler interconnections.
|
INSP-Sprinkler Rough-in | 12/7/2010 | 12/8/2010 | 12/8/2010 | A | PASS |
Troy Cobbley
|
|
|
The rough-in inspection for the three pendant heads in the second floor corridor is passed. They can now be recovered.
|
INSP-Sprinkler Rough-in/Hydro | 12/7/2010 | 12/7/2010 | 12/7/2010 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro test passed for the service area. The sprinkler rough-in is complete for the service area except for the piping on the second floor corridor has been covered and can not be inspected. This piping will need to be exposed for inspection. The issue came up on finaling this permit when the service area was complete. This can not be done since the new addition (service area) and the existing building are under the same permit and the same scope of work. All of the remaining work would need to be completed or the sprinkler plans, possibly fire alarm plans, including the building plans, would need to be resubmitted to modify the scope of work to match the installed work.
|
INSP-Sprinkler Rough-in | 12/2/2010 | 12/3/2010 | 12/3/2010 | P | FAIL |
Forrest France
|
|
|
Overhead hydrostatic test failed due to 7 psi pressure loss at the guage. Manifold and FDC hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 11/15/2010 | 11/16/2010 | 11/16/2010 | P | PASS |
Troy Cobbley
|
|
|
The underground hydro test passed with leakage acceptable per NFPA 13 chapter 10. The underground flush passed. The overhead rough-in for the Service Bay/Product/Electrical Room passed with the exception of the redline corrections noted on the city approved plans which include the need for an aux. drain, missing flexible cplgs.
|
INSP-Supply line flush | 11/10/2010 | 11/10/2010 | 11/10/2010 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was for the hydro test of the underground supply. I arrived at the project and found visible movement on the pressure guage. Jeff was in the process of locating the leak. No testing was performed.
|