Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR10-00512
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 3176 S DENVER WAY
Project NameST LUKE'S REFERENCE LABORATORY
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of changing all standard response sprinklers to quick response sprinklers. All piping to remain as is. Rooms shown with solid lines are new walls. The rooms with new walls have new arm overs. The existing dry valve and deluge valve shown on drawing Fp3 was removed under permit FIR10-00125


Building Department Scope:

Plan Modification - 10/5/10 - Due to mold mitigation and abatement, new windows and exterior wall finish & sheathing are being added to scope of work as approved under Modification of DRH09-00259. New exterior envelope components to comply with 2006 IECC. PLAN MODIFICATION 9/10/10 - SCOPE OF WORK REDUCED DUE TO FINANCIAL CONSTRAINTS. EXTERIOR MODIFICATIONS AND CANOPY ADDITIONS DELETED; INTERIOR FINISHES WITHIN ROOMS MARKED "FUTURE" TO REMAIN AS-IS; INTERIOR RESTROOM FINISHES & DIVIDERS TO REMAIN UNCHANGED; MISCELLANEOUS ARCH., MECH., ELECT., MINOR CHANGES OR SUBSTITUTIONS FOR COST SAVINGS. ALL ORIGINAL PLAN REVIEW COMMENTS OF ALL AGENCIES FOR ITEMS NOT REMOVED FROM SCOPE OF WORK ARE STILL APPLICABLE. ALL EXITING SYSTEM COMPONENTS (DOOR WIDTH, HARDWARE, CLEAR FLOOR SPACE, DOOR SWING, EXIT LIGHTING AND EMERGENCY LIGHTING, ETC. SHALL BE COMPLIANT WITH CURRENT CODE FOR LIFE SAFETY / EGRESS. To remodel an existing two story 31,625 sq. ft. building into a medical laboratory per approved plans. Demolition work is under separate permit, BLD09-02080. Work to include construction of interior walls in conjunction with remaining existing walls to create office, work, laboratory and support areas; conference / training room on second floor with existing offices; upgrade restrooms, showers, drinking fountains, doors, door hardware and clear floor spaces & latch side clearance at all doors; work on electrical, mechanical, plumbing, sprinkler, alarm and security systems to comply with current adopted codes and ordinances. Separate applications and permits required for sprinkler & alarm system modifications as regulated by the fire department, before being worked on. NOTE: This building is fully fire sprinklered with all heads being changed to quick response to allow non-rated corridors. drs

Fire Sprinkler System Design/Spacing:

Hydraulics were neither supplied nor required. The flow test information is S-65, R-20 & Q-3500 06-06-2010. Second floor is a 4”x4”x2” grid. Portions of the first floor is a 6”x4”x2” grid. The first floor also has a 6” & 4” loop. The existing demand on the first floor was .20/130 Sqft the new design is based on .10/225 Sqft. The existing demand on the second floor was .29/100 Sqft the new design is based on .10/225 Sqft.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/20/20111/21/20111/21/2011APASS
DetailsForrest France
Final inspection passed, adjustments and corrections finished. Combustible decking at the roof to be removed entirely by general contractor as discussed.
INSP-Sprinkler Rough-in1/20/20111/20/20111/20/2011PPART
DetailsForrest France
Provide missing pendent head at the gas room, flow switch did not pass operational test, riser is overdue annual inspection, platform at the roof must meet NFPA 13 2007 sec. 8.15.6.
INSP-Final Inspection1/18/20111/19/20111/19/2011APART
DetailsForrest France
For verification of previous c/n items including FDC relocation, rooms without ceilings, QR head at one mech. closet, etc. Discussed riser monitoring, schedule for final acceptance testing.
INSP-Sprinkler Rough-in12/23/201012/23/201012/23/2010APART
DetailsForrest France
Noted two heads at a second floor utility room to be changed to quick response type sprinklers.
INSP-Sprinkler Rough-in/Hydro12/21/201012/22/201012/22/2010APART
DetailsForrest France
Overhead hydrostatic testing passed. Noted obstructed FDC by the new concrete landing and guard rail, two rooms at the second floor are missing drop ceilings, remainder of combustible decking at the roof is not protected.
INSP-Sprinkler Rough-in12/2/201012/2/201012/6/2010PPART
DetailsForrest France
Okay to cover remainder of grid ceiling areas, spacing corrections finished.
INSP-Sprinkler Rough-in11/30/201012/1/201012/1/2010APART
DetailsForrest France
Some corrections finished- still need to relocate two overspaced pendent heads as previously noted.
INSP-Sprinkler Rough-in11/23/201011/23/201011/26/2010PPART
DetailsForrest France
See approved plan set for locations okayed to cover- noted some areas at the north half in need of adjustment or revision.
INSP-Sprinkler Rough-in11/10/201011/10/201011/11/2010PPART
DetailsForrest France
See approved plan set sheet FP 2 for locations inspected and approved for cover marked with today's date. Two heads to be added as discussed at the conference room.
INSP-Sprinkler Rough-in10/20/201010/21/201010/22/2010APART
DetailsForrest France
See stamped plan set for initialed locations marked with today's date approved for cover at sheetrock ceiling areas on the first and second floor levels.