INSP-Final Inspection | 1/20/2011 | 1/21/2011 | 1/21/2011 | A | PASS |
Forrest France
|
|
|
Final inspection passed, adjustments and corrections finished. Combustible decking at the roof to be removed entirely by general contractor as discussed.
|
INSP-Sprinkler Rough-in | 1/20/2011 | 1/20/2011 | 1/20/2011 | P | PART |
Forrest France
|
|
|
Provide missing pendent head at the gas room, flow switch did not pass operational test, riser is overdue annual inspection, platform at the roof must meet NFPA 13 2007 sec. 8.15.6.
|
INSP-Final Inspection | 1/18/2011 | 1/19/2011 | 1/19/2011 | A | PART |
Forrest France
|
|
|
For verification of previous c/n items including FDC relocation, rooms without ceilings, QR head at one mech. closet, etc. Discussed riser monitoring, schedule for final acceptance testing.
|
INSP-Sprinkler Rough-in | 12/23/2010 | 12/23/2010 | 12/23/2010 | A | PART |
Forrest France
|
|
|
Noted two heads at a second floor utility room to be changed to quick response type sprinklers.
|
INSP-Sprinkler Rough-in/Hydro | 12/21/2010 | 12/22/2010 | 12/22/2010 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic testing passed. Noted obstructed FDC by the new concrete landing and guard rail, two rooms at the second floor are missing drop ceilings, remainder of combustible decking at the roof is not protected.
|
INSP-Sprinkler Rough-in | 12/2/2010 | 12/2/2010 | 12/6/2010 | P | PART |
Forrest France
|
|
|
Okay to cover remainder of grid ceiling areas, spacing corrections finished.
|
INSP-Sprinkler Rough-in | 11/30/2010 | 12/1/2010 | 12/1/2010 | A | PART |
Forrest France
|
|
|
Some corrections finished- still need to relocate two overspaced pendent heads as previously noted.
|
INSP-Sprinkler Rough-in | 11/23/2010 | 11/23/2010 | 11/26/2010 | P | PART |
Forrest France
|
|
|
See approved plan set for locations okayed to cover- noted some areas at the north half in need of adjustment or revision.
|
INSP-Sprinkler Rough-in | 11/10/2010 | 11/10/2010 | 11/11/2010 | P | PART |
Forrest France
|
|
|
See approved plan set sheet FP 2 for locations inspected and approved for cover marked with today's date. Two heads to be added as discussed at the conference room.
|
INSP-Sprinkler Rough-in | 10/20/2010 | 10/21/2010 | 10/22/2010 | A | PART |
Forrest France
|
|
|
See stamped plan set for initialed locations marked with today's date approved for cover at sheetrock ceiling areas on the first and second floor levels.
|