INSP-Final Inspection | 2/1/2011 | 2/1/2011 | 2/1/2011 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/18/2011 | 1/19/2011 | 1/19/2011 | A | FAIL |
Troy Cobbley
|
|
|
Many of the sprinkler pendants are obstructed by the light fixtures. Per the residential obstruction chart a minimum distance of 3' is needed.
|
INSP-Sprinkler Rough-in | 1/6/2011 | 1/6/2011 | 1/6/2011 | P | PASS |
Troy Cobbley
|
|
|
The new wet system piping supply, up to the connection point, is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 12/28/2010 | 12/29/2010 | 12/30/2010 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro test of the wet and dry systems passed.
|
INSP-Sprinkler Rough-in | 12/7/2010 | 12/7/2010 | 12/7/2010 | P | PASS |
Troy Cobbley
|
|
|
The re-inspect of the wet system passed. The correction items for the dry system still need to be addressed. The sprinkler piping in the new addition can be covered.
|
INSP-Sprinkler Rough-in | 12/6/2010 | 12/6/2010 | 12/6/2010 | P | FAIL |
Troy Cobbley
|
|
|
The wrong upright sprinkler heads have been installed. The attice heads appear to be overspaced from the wall, in the attic, at the south end of the attic. The pendant heads in three bathrooms are not providing sprinkler coverage in the shower areas. The transition from 1 1/4" pipe to 1 1/2" pipe is in the wrong location. The additional elbows installed in the wet system are ok per tim. Todays inspection was just for the new south addition and not for any of the existing interior work.
|
INSP-Final Inspection | 1/28/2011 | 1/28/2011 | | P | |
Tim Frost
|
|
|
Mike M is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|