INSP-Final Inspection | 4/4/2011 | 4/4/2011 | 4/4/2011 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 4/1/2011 | 4/4/2011 | 4/4/2011 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 3/24/2011 | 3/28/2011 | 3/28/2011 | A | FAIL |
Troy Cobbley
|
|
|
The forward flush passed. The other items from the previous correction notice needs addressed.
|
INSP-Final Inspection | 3/23/2011 | 3/24/2011 | 3/24/2011 | A | FAIL |
Forrest France
|
|
|
Final pending forward flow test sufficient to meet system demand, reliable heating at the riser room to maintain ambient temperature above 40 deg., signage at the doors to the riser. Alarm interconnections tested okay.
|
FIR-Aging Inspection | 3/23/2011 | 3/23/2011 | 3/23/2011 | P | CANC |
Troy Cobbley
|
|
|
wrong inspection type set up.
|
INSP-Sprinkler Rough-in | 3/23/2011 | 3/23/2011 | 3/23/2011 | P | PASS |
Troy Cobbley
|
|
|
The lighting obstructions have been addressed and the extended coverage head is ok. Items needing addressed are the typical final inspection items such as tagging, signage, backflow certification and forward flow test.....ect
|
INSP-Sprinkler Rough-in/Hydro | 3/14/2011 | 3/14/2011 | 3/14/2011 | P | PASS |
Troy Cobbley
|
|
|
The wet system hydro test passed.
|
INSP-Sprinkler Rough-in | 3/10/2011 | 3/10/2011 | 3/10/2011 | P | PASS |
Troy Cobbley
|
|
|
Remaining sprinkler rough-in passed. Noted additional fittings affecting remote areas 2 and 3 but per Tim the hydraulic calculations are adequate. I also noted side wall heads under overhead doors that were not shown on the plans. One door at the east end of the service bay is going to be provided with an extended coverage sidewall that will need to be field approved. I also noted that the existing pendant sprinklers in the sales area are being blocked by suspended light fixtures. This problem will need to be addressed prior to final sign off. It appears that if the lights are mounted to the ceiling they will no longer be an obstruction.
|
INSP-Sprinkler Rough-in/Hydro | 3/9/2011 | 3/9/2011 | 3/10/2011 | A | PART |
Forrest France
|
|
|
24 hr. pneumatic testing of the dry system passed with no pressure loss at the guage.
|
INSP-Sprinkler Rough-in | 3/8/2011 | 3/8/2011 | 3/9/2011 | P | PART |
Forrest France
|
|
|
Begin 24 hr. pneumatic test of the dry system at 10:30 AM 3/8 @ 42psig.
|
INSP-Sprinkler Rough-in | 1/21/2011 | 1/21/2011 | 1/21/2011 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for location, with todays date, where sprinkler piping is ok to cover. As-builts are going to be required showing the pipe routing changes.
|
INSP-Sprinkler Rough-in | 1/12/2011 | 1/13/2011 | 1/13/2011 | A | PASS |
Troy Cobbley
|
|
|
The piping in the main/front canopy can be covered. See the city approved plans for location with todays date.
|
INSP-Sprinkler Rough-in | 1/6/2011 | 1/7/2011 | 1/7/2011 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the location where the sprinkler piping can be covered. It is marked with todays date.
|
INSP-Sprinkler Rough-in | 1/6/2011 | 1/6/2011 | 1/6/2011 | P | CANC |
Troy Cobbley
|
|
|
To be cancelled per Don Forrester ###-####
|