INSP-Final Inspection | 10/6/2011 | 10/7/2011 | 10/7/2011 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 10/4/2011 | 10/5/2011 | 10/6/2011 | P | FAIL |
Troy Cobbley
|
|
|
The forward flush passed. Can final this permit when the interconnections with the fire control panel have been verified. I was unable to verify interconnections due to fire alarm system issues.
|
INSP-Final Inspection | 10/3/2011 | 10/4/2011 | 10/4/2011 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Stephan Phone #: ###-####
|
INSP-Sprinkler Rough-in | 9/23/2011 | 9/23/2011 | 9/23/2011 | P | PASS |
Troy Cobbley
|
|
|
All items have been corrected except the plan modifications are needed to reflect the re-routing of mains, different branchline sizing, additional heads in remote areas and additional fittings that will effect remote areas. Final sign off will not be given until these plans have been reviewed, issued and any required modifications to the installed system addressed.
|
INSP-Sprinkler Rough-in | 9/20/2011 | 9/21/2011 | 9/21/2011 | A | PASS |
Troy Cobbley
|
|
|
The remaining warehouse area rough-in passed. See the city approved plans for the red lined comments that need corrected. Resubmittals are needed to show the piping size changes and additional heads and fittings in the remote areas.
|
INSP-Sprinkler Rough-in/Hydro | 9/20/2011 | 9/20/2011 | 9/20/2011 | P | PASS |
Troy Cobbley
|
|
|
The hydro test on the remaining riser pass. Also another portion of the warehouse was inspected with minor corrections noted.
|
INSP-Sprinkler Rough-in/Hydro | 9/8/2011 | 9/9/2011 | 9/9/2011 | P | PART |
Tim Frost
|
|
|
Passed hydro on N Warehouse and First Floor
Failed Drive Thru/S Warehouse
|
INSP-Supply line flush | 8/24/2011 | 8/25/2011 | 8/25/2011 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/24/2011 | 8/25/2011 | 8/25/2011 | A | PASS |
Troy Cobbley
|
|
|
The underground supply line hydro test passed.
|
INSP-Sprinkler Rough-in | 8/15/2011 | 8/15/2011 | 8/15/2011 | P | PASS |
Troy Cobbley
|
|
|
Second floor sprinkler piping will be ok to cover when the stop work order for the project related fire alarm plans is lifted. I agreed to allow boarders with Mike the job superintendant.
|
INSP-Sprinkler Rough-in | 8/12/2011 | 8/15/2011 | 8/15/2011 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the warehouse area, marked with todays date, where the sprinkler piping rough-in has passed.Terry is modifying the locations of 5 earthquake braces so that they match the plans.
|
INSP-Sprinkler Rough-in | 8/10/2011 | 8/11/2011 | 8/11/2011 | A | PASS |
Troy Cobbley
|
|
|
The piping at the second floor, over the lobby stairs, is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 8/2/2011 | 8/2/2011 | 8/2/2011 | P | PASS |
Troy Cobbley
|
|
|
First floor office piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2011 | 7/12/2011 | 7/12/2011 | A | PASS |
Troy Cobbley
|
|
|
The corrections have been made for the office area sprinkler piping rough-in. Another rough-in inspection will still need to be performed for the installation of the pendant arm-overs prior to an approval for cover.
|
INSP-Sprinkler Rough-in/Hydro | 7/7/2011 | 7/8/2011 | 7/8/2011 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was for the second floor of the office area. There were two retaining strap issues and the 3" sprinkler main was missing all of the trapeze hangers. The hardlid area in the north east corner is ok to cover. Also a separate inspection will be required when the arm-overs and drops have been installed in the gridded ceiling areas.
|
INSP-Sprinkler Rough-in | 7/7/2011 | 7/7/2011 | 7/7/2011 | A | PASS |
Troy Cobbley
|
|
|
Inspection was for the first floor of the office area. Previous items on the correction notice have been addressed except for the missing hanger. This rough-in is for the system piping only. The arm overs and pendant heads have not been installed and will need to be verified with a separate inspection. Revised hydraulic calculations and plans need to be submittted to Tim Frost for verification of the piping changes noted at the first rough-in inspection.
|
INSP-Sprinkler Rough-in | 6/28/2011 | 6/29/2011 | 6/29/2011 | P | NR |
Forrest France
|
|
|
Partial walkthrough of the 1st floor office area only- noted field modifications at some areas in branchline routing, head location/type, relocated aux drain, etc., noted one missing head at a closet, missing hanger, heads, armovers and drops are not yet installed at some areas. Discussed elevator hoistway and SW head at the exterior canopy. Field mods will require as-built or plan modification depending on calcs.
|
INSP-Sprinkler Rough-in | 5/24/2011 | 5/25/2011 | 5/25/2011 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping cover passed. Piping can be covered.
|