Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR11-00095
StatusFinaled
Name ALLIED GENERAL FIRE & SECURITY
Site Address 601 N PHILLIPPI ST
Project NameSTEIN DISTRIBUTING
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of protecting a warehouse storing beer and beverages. (Plan Mod #1) General revisions due to as built conditions including: showing the 4” main in the correct position on drawing 2, showing the FDC in the correct position on drawing 1, add 2 sprinklers below a mezzanine on drawing 3, delete hsw below doors because the doors were changed to roll up type, switched the bfp to 6” instead of 8”. All new hydraulics were provided. Building Permit Scope: Stein Distributing - Reconstruction and Addition - To rebuild an existing warehouse and two-story office building that was previously demolished under permit BLD10-02537. The major portion of the warehouse roof structure was kept, as well as, a section of the north exterior double tee concrete walls and some interior bearing walls. The warehouse floor area will be increased by approximately 15,295 square feet (61,140 sq. ft to 76,435 sq. ft.). The two-story office portion of the building will be completely rebuilt. This permit also includes related site improvements. The warehouse is constructed of concrete tilt-up exterior wall with a wood framed roof. The office portion of the building is constructed on noncombustible metal framing and metal stud walls and partitions. First Floor: 76,435 sq. ft. + 1,185 sq. ft. storage mezzanine Second Floor (all office) 10,845 sq. ft. Building Total: 87,280 sq. ft.. The foundation was done under permit BLD10-02676. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/6/201110/7/201110/7/2011APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection10/4/201110/5/201110/6/2011PFAIL
DetailsTroy Cobbley
The forward flush passed. Can final this permit when the interconnections with the fire control panel have been verified. I was unable to verify interconnections due to fire alarm system issues.
INSP-Final Inspection10/3/201110/4/201110/4/2011ACANC
DetailsTroy Cobbley
Cancel per Stephan Phone #: ###-####
INSP-Sprinkler Rough-in9/23/20119/23/20119/23/2011PPASS
DetailsTroy Cobbley
All items have been corrected except the plan modifications are needed to reflect the re-routing of mains, different branchline sizing, additional heads in remote areas and additional fittings that will effect remote areas. Final sign off will not be given until these plans have been reviewed, issued and any required modifications to the installed system addressed.
INSP-Sprinkler Rough-in9/20/20119/21/20119/21/2011APASS
DetailsTroy Cobbley
The remaining warehouse area rough-in passed. See the city approved plans for the red lined comments that need corrected. Resubmittals are needed to show the piping size changes and additional heads and fittings in the remote areas.
INSP-Sprinkler Rough-in/Hydro9/20/20119/20/20119/20/2011PPASS
DetailsTroy Cobbley
The hydro test on the remaining riser pass. Also another portion of the warehouse was inspected with minor corrections noted.
INSP-Sprinkler Rough-in/Hydro9/8/20119/9/20119/9/2011PPART
DetailsTim Frost
Passed hydro on N Warehouse and First Floor
Failed Drive Thru/S Warehouse
INSP-Supply line flush8/24/20118/25/20118/25/2011APASS
DetailsTroy Cobbley
Underground supply line flush passed.
INSP-Sprinkler Rough-in/Hydro8/24/20118/25/20118/25/2011APASS
DetailsTroy Cobbley
The underground supply line hydro test passed.
INSP-Sprinkler Rough-in8/15/20118/15/20118/15/2011PPASS
DetailsTroy Cobbley
Second floor sprinkler piping will be ok to cover when the stop work order for the project related fire alarm plans is lifted. I agreed to allow boarders with Mike the job superintendant.
INSP-Sprinkler Rough-in8/12/20118/15/20118/15/2011APASS
DetailsTroy Cobbley
See the city approved plans for the warehouse area, marked with todays date, where the sprinkler piping rough-in has passed.Terry is modifying the locations of 5 earthquake braces so that they match the plans.
INSP-Sprinkler Rough-in8/10/20118/11/20118/11/2011APASS
DetailsTroy Cobbley
The piping at the second floor, over the lobby stairs, is ok to cover.
INSP-Sprinkler Rough-in/Hydro8/2/20118/2/20118/2/2011PPASS
DetailsTroy Cobbley
First floor office piping is ok to cover.
INSP-Sprinkler Rough-in/Hydro7/11/20117/12/20117/12/2011APASS
DetailsTroy Cobbley
The corrections have been made for the office area sprinkler piping rough-in. Another rough-in inspection will still need to be performed for the installation of the pendant arm-overs prior to an approval for cover.
INSP-Sprinkler Rough-in/Hydro7/7/20117/8/20117/8/2011APART
DetailsTroy Cobbley
Todays inspection was for the second floor of the office area. There were two retaining strap issues and the 3" sprinkler main was missing all of the trapeze hangers. The hardlid area in the north east corner is ok to cover. Also a separate inspection will be required when the arm-overs and drops have been installed in the gridded ceiling areas.
INSP-Sprinkler Rough-in7/7/20117/7/20117/7/2011APASS
DetailsTroy Cobbley
Inspection was for the first floor of the office area. Previous items on the correction notice have been addressed except for the missing hanger. This rough-in is for the system piping only. The arm overs and pendant heads have not been installed and will need to be verified with a separate inspection. Revised hydraulic calculations and plans need to be submittted to Tim Frost for verification of the piping changes noted at the first rough-in inspection.
INSP-Sprinkler Rough-in6/28/20116/29/20116/29/2011PNR
DetailsForrest France
Partial walkthrough of the 1st floor office area only- noted field modifications at some areas in branchline routing, head location/type, relocated aux drain, etc., noted one missing head at a closet, missing hanger, heads, armovers and drops are not yet installed at some areas. Discussed elevator hoistway and SW head at the exterior canopy. Field mods will require as-built or plan modification depending on calcs.
INSP-Sprinkler Rough-in5/24/20115/25/20115/25/2011PPASS
DetailsTroy Cobbley
Underground supply piping cover passed. Piping can be covered.