INSP-Final Inspection | 8/29/2011 | 8/29/2011 | 8/29/2011 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 8/25/2011 | 8/25/2011 | 8/25/2011 | P | FAIL |
Troy Cobbley
|
|
|
Forward flush passed. This project can be finaled when the tamper switches on the wet system are reporting to the central station.
|
INSP-Final Inspection | 8/24/2011 | 8/24/2011 | 8/24/2011 | P | FAIL |
Troy Cobbley
|
|
|
The wet system tamper switches are not reporting to the central station. Need to perform the forward flush.
|
INSP-Final Inspection | 8/22/2011 | 8/23/2011 | 8/23/2011 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for the duct smoke detector shutdown which passed.
|
INSP-Final Inspection | 8/19/2011 | 8/19/2011 | 8/19/2011 | P | CANC |
Forrest France
|
|
|
Overbooked
|
INSP-Final Inspection | 8/16/2011 | 8/16/2011 | 8/16/2011 | P | FAIL |
Troy Cobbley
|
|
|
All correction items have been addressed. Project can be finaled when the fire alarm interconnections have been tested.
|
INSP-Sprinkler Rough-in | 8/15/2011 | 8/15/2011 | 8/15/2011 | P | FAIL |
Troy Cobbley
|
|
|
To final this project the pendant on the second floor that is blocked by the column needs to be addressed, the resubmittal for the second floor stockroom pipe routing changes and a walk through on the lower level storage area at the truck dock. Also need the earthquake spacing ok'd by tim frost.
|
INSP-Sprinkler Rough-in/Hydro | 8/11/2011 | 8/12/2011 | 8/12/2011 | P | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/2/2011 | 8/3/2011 | 8/2/2011 | A | CANC |
Troy Cobbley
|
|
|
Hydo//Joe ###-#### -- cancelled per Troy Cobbley 8/2/11 leg
|
INSP-Sprinkler Rough-in | 7/21/2011 | 7/22/2011 | 7/22/2011 | P | PASS |
Troy Cobbley
|
|
|
Request to rough-to-cover inspection for several areas is approved. See the city approved "plan modification" for areas marked "ok". I let Joe know that the maximum spacing for the lateral bracing on the lower level is 30' and 80' for the longitudinals and to refer to nfpa 13 table 9.3.5.3.2 (a)
|
INSP-Sprinkler Rough-in | 7/13/2011 | 7/14/2011 | 7/14/2011 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was to verify that several of the previous corrections had been addressed on the lower level. They have been marked "ok" in red ink. One pendant still had not been installed in a hard lid and the earthquake bracing for the mains was incorrect.
|
INSP-Sprinkler Rough-in | 7/11/2011 | 7/11/2011 | 7/11/2011 | P | PART |
Troy Cobbley
|
|
|
The open sales area of the lower level is ok to cover except for locations where earthquake bracing is required to be verified. None of the smaller, outer rooms, have been inspected for cover. Several locations on the sales floor require modified sprinkler coverage. There is atleast one concealed space with no sprinkler protection but with exposed wood. Also the 2 1/2" branchlines in the lower and upper level areas require lateral earthquake bracing.
|
INSP-Sprinkler Rough-in | 7/7/2011 | 7/8/2011 | 7/8/2011 | P | PART |
Troy Cobbley
|
|
|
The majority of the area looked at this afternoon was the Upper Level. There are still several outstanding items which include missing retaining straps, overspaced heads, missing heads, need for trapeze hangers in the warehouse and possible obstructions caused by the valances in the display areas. The piping arrangement does not match the plans so plan modifications will be required prior to a final sign off. The lower level truck dock dry system was inspected today as well. Revised hydraulic calculations were submitted and approved by Tim Frost for this area. I need verification that the top beam clamps have been welded to the beam flange or new hangers installed. Tim Frost noted a Trash Compactor area which is lacking sprinkler protection.
|
INSP-Sprinkler Rough-in | 7/7/2011 | 7/8/2011 | 7/8/2011 | A | PASS |
Troy Cobbley
|
|
|
The second floor elevator room and the area around the escalator, at the second floor, is ok to cover.
|
INSP-Sprinkler Rough-in | 7/6/2011 | 7/6/2011 | 7/6/2011 | P | PASS |
Troy Cobbley
|
|
|
Only a small area of the second floor near the escalator is ok for cover. The other areas do not have the T-bar or the pendant heads installed. I let Joe know that what appears to be soffits at the outer edge of the sales floor may cause obstructions to the sprinkler coverage when installed.
|
INSP-Sprinkler Rough-in | 6/30/2011 | 7/1/2011 | 7/1/2011 | A | PASS |
Troy Cobbley
|
|
|
The first floor Jewelery area (6) heads and the three heads at the north side of the water curtain are ok to cover.
|
INSP-Sprinkler Rough-in | 6/29/2011 | 6/30/2011 | 7/1/2011 | P | FAIL |
Troy Cobbley
|
|
|
Piping was not complete in Jewelry area when I stopped at 2:00pm. Rescheduled for tomorrow.
|
INSP-Sprinkler Rough-in | 6/21/2011 | 6/23/2011 | 6/23/2011 | A | DONE |
Forrest France
|
|
|
Reference inspection notes per T. Frost completed 6/22.
|
INSP-Sprinkler Rough-in | 6/21/2011 | 6/22/2011 | 6/22/2011 | A | FAIL |
Forrest France
|
|
|
Performed partial inspection on the second floor. Inspected sales permitter. Did not inspect rooom on the outside sales area. Did not inspect the middle of the sales. Prints are marked in red for sprinklers that were inspected. Inspection, failed. There were over spaced and missing sprinklers. The prints are marked accordingly.
|