INSP-Final Inspection | 9/12/2011 | 9/13/2011 | 9/13/2011 | A | PASS |
Forrest France
|
|
|
Field verified repair of one notification device at the 1st floor elevator lobby. Fire alarm permit final approved.
|
INSP-Final Inspection | 9/6/2011 | 9/7/2011 | 9/13/2011 | A | PART |
Forrest France
|
|
|
Completed remainder of testing for the scope of permit work.
|
INSP-Alarm Testing | 9/12/2011 | 9/12/2011 | 9/12/2011 | P | PART |
Forrest France
|
|
|
Remainder of the new SD at the basement and 1st floor levels tested okay. Final pending repair of one non-functional notification appliance at the 1st floor elevator lobby.
|
INSP-Final Inspection | 8/31/2011 | 9/1/2011 | 9/1/2011 | A | DEFR |
Forrest France
|
|
|
scott - please call 45 minutes prior Phone #: ###-####
|
INSP-Final Inspection | 8/16/2011 | 8/17/2011 | 8/17/2011 | A | PART |
Forrest France
|
|
|
Tested new smoke detection at the 3rd floor east and south towers and 2nd floor central and north floor areas. Reinspected door holders at the 5th floor for functionality after repairs.
|
INSP-Final Inspection | 8/15/2011 | 8/16/2011 | 8/16/2011 | P | DEFR |
Forrest France
|
|
|
scott Phone #: ###-####
|
INSP-Final Inspection | 8/2/2011 | 8/3/2011 | 8/3/2011 | A | PART |
Forrest France
|
|
|
Site testing completed for new smoke detectors at the 8th, 7th, 6th and 5th floors. Descriptor at address 78 (5th) to accurately indicate the room located. Noted door holds at the 5th floor did not release upon fire alarm activation. Discussed inspection schedule for the remainder of the project.
|
INSP-Conference | 7/28/2011 | 7/28/2011 | 7/28/2011 | P | DONE |
Forrest France
|
|
|
Regarding project inspection schedule.
|