INSP-Final Inspection | 10/4/2011 | 10/4/2011 | 10/4/2011 | P | PASS |
Forrest France
|
|
|
C/N items finished. Final walkthrough passed. Permit finaled.
|
INSP-Final Inspection | 10/3/2011 | 10/3/2011 | 10/3/2011 | P | FAIL |
Forrest France
|
|
|
Missing escutcheon at the main level, missing one SW head at a basement bedroom closet, need to secure control valves in the open position at the riser. Outside bell tested okay.
|
INSP-Sprinkler Rough-in | 7/29/2011 | 7/29/2011 | 7/29/2011 | P | PART |
Forrest France
|
|
|
Field verified approved revised plans match installation. Cold cavity protection is satisfactory with the exception of one area at the main level study room #2. Contractor to repair prior to sheetrock cover. Overhead rough-in approved for cover.
|
INSP-Sprinkler Rough-in | 7/29/2011 | 7/29/2011 | 7/29/2011 | P | CANC |
Forrest France
|
|
|
ok to cover--Don Phone #: ###-####
|
INSP-Sprinkler Rough-in | 7/25/2011 | 7/26/2011 | 7/26/2011 | A | FAIL |
Troy Cobbley
|
|
|
The rough-in itself appears ok but extensive pipe routing changes have been made. Plan modifications are required. Per Tim Frost the sidewall head show at the garage door to the residence can be changed to a pendant. I verified that the pendant heads will provide coverage under the soffits in the living room and in the entry ways to the two bedrooms in the lower level. No tenting has been done yet. I let Don know that a approval for cover would not be given until the plans are re-approved and the tenting was approved. Also the backflow preventor installed is not the one that was submitted on. No underground piping from the street to the bottom of the backflow was inspected or even present.
|
INSP-Sprinkler Rough-in | 7/25/2011 | 7/25/2011 | 7/25/2011 | P | NR |
Forrest France
|
|
|
|