Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberFIR11-00382
StatusFinaled
Name TRI STATE ELECTRIC
Site Address 601 N PHILLIPPI ST
Project NameSTEIN DISTRIBUTING
Customer Number 
ePlanReviewNo
Description
10-10-11 PLAN MODIFICATION 2 (no initiating devices affected): This plan modification is to include release of a magnetic door lock on general alarm.

(10-6-2011) – Plan modification submitted indicating new location of fire alarm panel, addition of initiating devices, addition of one new circuit on one line diagram, and addition of notification devices.
Modifications are indicated in red on plans. Final approval will be subject to satisfactory field inspection by the PDS Fire inspector. *SJA*

8-24-11: This fire alarm permit is to provide a manual fire alarm system required due to over 100 occupant load on the floors above the lowest level of exit discharge. The system shall include a manual pull station, smoke and heat detectors for elevator recall/shunt trip functions, duct detectors for HVAC shutdown/monitoring, full notification, and sprinkler system monitoring.

Associated building permit: BLD10-02870 Stein Distributing - Reconstruction and Addition - To rebuild an existing warehouse and two story offices building that was previously demolished under permit BLD10-02537. The major portion of the warehouse roof structure was kept, as well as, a section of the north exterior double tee concrete walls and some interior bearing walls. The warehouse floor area will be increased by approximately 15,295 square feet (61,140 sq. ft to 76,435 sq. ft.). The two story office portion of the building will be completely rebuilt. This permit also includes related site improvements. The warehouse is constructed of concrete tilt-up exterior wall with a wood framed roof. The office portion of the building is constructed on noncombustible metal framing and metal stud walls and partitions. First Floor: 76,435 sq. ft. + 1,185 sq. ft. storage mezzanine Second Floor (all office) 10,845 sq. ft. Building Total: 87,280 sq. ft. The foundation was done under permit BLD10-02676. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/10/201110/11/201110/11/2011APASS
DetailsTroy Cobbley
Permit finaled
INSP-Alarm Testing10/7/201110/10/201110/10/2011ADONE
DetailsTroy Cobbley
All items have been tested. Need the plan modifications, and any changes corrected, and then this permit can be finaled.
INSP-Final Inspection10/7/201110/7/201110/7/2011PFAIL
DetailsTroy Cobbley
Phone lines have been fixed. The sprinkler system interconnections (tamper switches, flow switches) tested ok and signals reported correctly.EOL voltages tested ok. The manual pull station is mounted too high and will need to be lowered.To finish the inspection the duct smoke detectors and elevator recall functions need to be tested. I found a door to a secured area on the second floor that shall meet the requirements of IFC 1008.1.4.4. The fire alarm plans need to be resubmitted showing this interconnected with the fire alarm panel as well as showing the correct flow switch and tamper switch counts. I also went over the map requirements for the facp with Clay.
INSP-Final Inspection10/7/201110/7/201110/7/2011AFAIL
DetailsTroy Cobbley
The phone lines on the fire alarm panel are not calling out on a primary line and a secondary line as required. Only one line is being used. Inspection stopped. No other items were tested.
INSP-Alarm Testing10/4/201110/5/201110/6/2011PFAIL
DetailsTroy Cobbley
No testing was done due to test reports and the NFPA 72 testing and inspection reports not being provided as per the review comments prior to an inspection. I did perform a walk through with the electrician and the fire alarm tech to verify audio visual spacing and candella settings. I found devices in several locations overspaced and additional devices needed in other areas. The fire alarm panel has also been relocated from the Electrical Room to the Server Room. A smoke and a heat detector have been added at the top of the elevator shaft. After a phone conversation with the fire alarm plan reviewer it was agreed that plan modifications are required prior to continuing an inspection. The main issue is the End of Line voltages have been calculated close to the acceptable limits. The device changes and panel relocation has the potential to have adverse effects on the calculations.
INSP-Alarm Testing9/29/201110/4/201110/4/2011PCANC
DetailsTroy Cobbley
rafe Phone #: ###-####