INSP-Final Inspection | 1/10/2012 | 1/11/2012 | 1/11/2012 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. I waited as tim set up the zone descriptions and responding address with central station. We retested to verify they received the correct signals. He will send me a confirmation email when the hardcopy documentation is sent to central station.
|
INSP-Final Inspection | 12/7/2011 | 12/7/2011 | 12/12/2011 | P | CANC |
Troy Cobbley
|
|
|
Tim is tracking down the access key and will reschedule.
|
INSP-Final Inspection | 11/9/2011 | 11/10/2011 | 11/10/2011 | A | FAIL |
Troy Cobbley
|
|
|
When I arrived on the job site the Netcon had changed from a 5 to a 6. Tim is going to install an antenna and reschedule.
|
INSP-Final Inspection | 11/9/2011 | 11/9/2011 | 11/9/2011 | P | CANC |
Troy Cobbley
|
|
|
Per tim the AES is only getting a 6 Netcon so he wanted to cancel the inspection. No inspection was performed.
|