INSP-Final Inspection | 11/1/2011 | 11/1/2011 | 11/1/2011 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 10/26/2011 | 10/26/2011 | 10/26/2011 | P | FAIL |
Troy Cobbley
|
|
|
Need the ceiling tile installed prior to a final sign off and as-builts need to be provided that match the actual installation.
|
INSP-Final Inspection | 10/7/2011 | 10/10/2011 | 10/10/2011 | P | FAIL |
Troy Cobbley
|
|
|
Project is not ready for a final inspection. Jeremy just needed a rough-in inspection but I found that the piping routing and pipe sizing is incorrect and all of the restrooms are labeled Upper Level Southwest. Provide as-builts with these corrections prior to another cover inspection.
|
INSP-Sprinkler Rough-in | 9/20/2011 | 9/21/2011 | 9/21/2011 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping in the womens restroom, first floor, is ok to cover. Two pendants are not changed to quick responce yet but will be checked at final. See red lines on city approved plans.
|