INSP-Final Inspection | 6/8/2012 | 6/8/2012 | 6/8/2012 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Conference | 5/18/2012 | 5/21/2012 | 5/21/2012 | A | CANC |
Troy Cobbley
|
|
|
Wrong permit called in for life safety conference.
|
INSP-Sprinkler Rough-in | 3/20/2012 | 3/21/2012 | 3/21/2012 | A | PASS |
Troy Cobbley
|
|
|
See the fourth floor of the city approved plans for additional rooms where the sprinkler piping can be covered. I noted that there was an open sprinkler pipe above the ceiling of the trash room.
|
INSP-Sprinkler Rough-in | 1/17/2012 | 1/17/2012 | 1/17/2012 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the west side, fourth floor, resident rooms where the sprinkler piping can be covered now that the tenting is done. Raul repaired the tenting in rooms 404, 407 and 408 while I waited. The approval for cover does not include the west side, fourth floor corridor as that piping has not been installed yet.
|
INSP-Sprinkler Rough-in | 1/13/2012 | 1/17/2012 | 1/17/2012 | A | FAIL |
Troy Cobbley
|
|
|
The tenting had only been completed in acouple of rooms. Will re-inspect when I come back for the underground flush this afternoon.
|
INSP-Sprinkler Rough-in/Hydro | 10/14/2011 | 10/17/2011 | 10/17/2011 | A | PASS |
Troy Cobbley
|
|
|
Only the IBR has been installed at this time. Piping is ok to cover.
|
INSP-Sprinkler Rough-in | 10/13/2011 | 10/13/2011 | 10/13/2011 | P | CANC |
Troy Cobbley
|
|
|
Overbooked - will have to be rescheduled
|