INSP-Final Inspection | 12/30/2011 | 1/3/2012 | 1/3/2012 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit work approved for final. Fire alarm panel interconnections for both alarm and supervisory conditions tested acceptable.
|
INSP-Final Inspection | 12/21/2011 | 12/22/2011 | 12/22/2011 | A | PART |
Forrest France
|
|
|
Final walkthrough completed including verification of previous C/N items, intermediate temp. heads at the unit heaters in the basement and missing DCVA support installed while on site, forward flow test passed. Final pending repair of the tamper switch at the PIV and project related fire alarm permit work for sprinkler monitoring.
|
INSP-Final Inspection | 12/20/2011 | 12/21/2011 | 12/21/2011 | P | NR |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/14/2011 | 12/14/2011 | 12/14/2011 | A | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2011 | 12/13/2011 | 12/13/2011 | A | PASS |
Troy Cobbley
|
|
|
OH Hydro for antifreeze system passed
|
INSP-Sprinkler Rough-in/Hydro | 12/7/2011 | 12/7/2011 | 12/7/2011 | P | FAIL |
Forrest France
|
|
|
Antifreeze system hydrostatic test failed due to visible leakage and a pressure drop at the guage.
|
INSP-Sprinkler Rough-in/Hydro | 12/7/2011 | 12/7/2011 | 12/7/2011 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic testing for the basement and 1st floor levels passed.
|
INSP-Sprinkler Rough-in | 12/6/2011 | 12/7/2011 | 12/7/2011 | A | PART |
Forrest France
|
|
|
Completed overhead inspection for the 1st floor. Correction items include; 3 upright heads at the antifreeze system elevated entryway west side, provide revised plans including changes for sprinkler protection at the test chamber 138 within the calc area and added sw heads for garage doors, add missing seismic bracing at the 3" main, verify correct size hangers for 4" main. Drop ceiling areas okayed for cover.
|
INSP-Sprinkler Rough-in | 12/5/2011 | 12/6/2011 | 12/7/2011 | A | PART |
Forrest France
|
|
|
Overhead rough-in for the basement level completed. Noted items include missing coverage below stairway adjacent to the elevator machine room, upright heads next to unit heaters need correct temp. rating, FDC piping slopes opposite of the ball drip at the check, approved plans indicate backflow is located at the riser- DCVA is remotely installed where the UG supply enters the building.
|
INSP-Sprinkler Rough-in/Hydro | 11/16/2011 | 11/17/2011 | 11/17/2011 | P | PASS |
Forrest France
|
|
|
UG fire supply line hydrostatic testing completed.
|
INSP-Supply line flush | 11/11/2011 | 11/15/2011 | 11/15/2011 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 11/3/2011 | 11/3/2011 | 11/3/2011 | P | PART |
Forrest France
|
|
|
Ref. stamped plan set for areas inspected to date.
|
INSP-Sprinkler Rough-in | 10/27/2011 | 10/31/2011 | 10/31/2011 | A | PART |
Forrest France
|
|
|
See approved plans for marked locations okayed for cover at sheetrock ceilings on the 1st floor.
|
INSP-Sprinkler Rough-in | 10/18/2011 | 10/18/2011 | 10/18/2011 | P | PART |
Forrest France
|
|
|
Regarding plan notes for bollards at the new PIV- to be installed per discussion.
|
INSP-Sprinkler Rough-in | 10/14/2011 | 10/17/2011 | 10/17/2011 | A | PART |
Forrest France
|
|
|
UG fire supply line okayed for cover. Note: PIV located 3' from the building approved per plan review.
|