INSP-Final Inspection | 6/8/2012 | 6/8/2012 | 6/8/2012 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Conference | 3/27/2012 | 3/28/2012 | 3/28/2012 | A | DONE |
Troy Cobbley
|
|
|
Mike and I discussed the project.
|
INSP-Sprinkler Rough-in/Hydro | 3/5/2012 | 3/6/2012 | 3/6/2012 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for three additional first floor rooms where the sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 3/2/2012 | 3/2/2012 | 3/2/2012 | A | PART |
Forrest France
|
|
|
Overhead installation at the 1st floor mechanical room 162, corridor 2A, and electrical 159 okay for cover with the agreement changes in pipe routing at room 162 are approved. Also inspected 2nd floor units 221 thru 224, internet cafe and barber 270. Noted missing coverage at the storage closet in the barber room. See plans for annotations.
|
INSP-Sprinkler Rough-in/Hydro | 3/1/2012 | 3/1/2012 | 3/2/2012 | P | NH |
Forrest France
|
|
|
please call when headded to the site . Phone #: ###-#### >> Inspection requested via web by Alicia Pauley
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2012 | 2/28/2012 | 2/28/2012 | A | PART |
Forrest France
|
|
|
Overhead work at the 3rd floor rooms 321-327 and the library room are approved for ceiling cover. Noted missing expansion joint at the 2" main on grid line 22. See plans for annotations.
|
INSP-Sprinkler Rough-in/Hydro | 2/24/2012 | 2/24/2012 | 2/24/2012 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for areas where the fourth floor piping is ok to cover. This includes the piping that has been modified to match the approved plans around the canopy area.
|
INSP-Sprinkler Rough-in/Hydro | 2/23/2012 | 2/23/2012 | 2/23/2012 | P | PART |
Troy Cobbley
|
|
|
Todays inspection was for several rooms on the fourth floor. Piping installed does not match the city approved plans in the three rooms around the exterior balcony. Piping can not be covered in this area.
|
INSP-Sprinkler Rough-in/Hydro | 2/16/2012 | 2/16/2012 | 2/16/2012 | P | PART |
Forrest France
|
|
|
Seismic braces at the 1st floor west end corridor 1 passed reinspection per plan detail. Rough-in at rooms 113 thru 117 okayed for cover as noted- sw heads at rooms 115, 116, 117 are not yet installed. Plans do not show a DSW at room 114.
|
INSP-Sprinkler Rough-in | 2/14/2012 | 2/15/2012 | 2/15/2012 | A | FAIL |
Troy Cobbley
|
|
|
No inspection was performed. Called the contact twice and left one message. Walked all four floors of the construction area looking for fitters. Did not final anyone.
|
INSP-Sprinkler Rough-in/Hydro | 2/14/2012 | 2/14/2012 | 2/14/2012 | P | CANC |
Troy Cobbley
|
|
|
Canceled and rescheduled for tomorrow per Raul voice message.
|
INSP-Sprinkler Rough-in/Hydro | 2/13/2012 | 2/13/2012 | 2/13/2012 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for piping locations on the second floor that are ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 2/9/2012 | 2/9/2012 | 2/9/2012 | A | PASS |
Troy Cobbley
|
|
|
The fourth floor insulation has been repaired. The piping can be covered in areas as marked on the plans with todays date.
|
INSP-Sprinkler Rough-in | 2/8/2012 | 2/8/2012 | 2/8/2012 | P | PART |
Troy Cobbley
|
|
|
The pendant head on the third floor has been relocated but the fourth floor tenting and the deflection of the piping has not been addressed.
|
INSP-Sprinkler Rough-in/Hydro | 2/8/2012 | 2/8/2012 | 2/8/2012 | A | FAIL |
Troy Cobbley
|
|
|
Could not make contact with the fitter/contractor either by phone or in person. Wander all four floors. No inspection was performed. I did conference with the fire alarm vendor.
|
INSP-Sprinkler Rough-in/Hydro | 2/7/2012 | 2/7/2012 | 2/7/2012 | P | PART |
Forrest France
|
|
|
Rough-in inspection for the west wing 3rd and 4th floors as marked with today's date on approved plans from the stairway to rooms 320 and 420 completed. Noted items include blocked head at unit 313, 1" branch line transitions from the common corridor to the apartments must meet deflection tables per the material specifications, riser feed at the stariways are incomplete, tenting is not adequate at several areas on the 4th floor.
|
INSP-Sprinkler Rough-in/Hydro | 2/1/2012 | 2/2/2012 | 2/2/2012 | A | PASS |
Troy Cobbley
|
|
|
The resident rooms for the first floor, west end, as marked on the plans are ok to cover. This does not include the corridor stand pipe supply due to the earth quake bracing not being complete.
|
INSP-Sprinkler Rough-in/Hydro | 1/30/2012 | 2/1/2012 | 2/1/2012 | A | CANC |
Troy Cobbley
|
|
|
1st floor is not ready. To be rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 1/30/2012 | 1/31/2012 | 2/1/2012 | P | CANC |
Troy Cobbley
|
|
|
Inspection was performed during the morning requested time slot.
|
INSP-Sprinkler Rough-in/Hydro | 1/30/2012 | 1/31/2012 | 1/31/2012 | A | PASS |
Troy Cobbley
|
|
|
The second floor west end piping can be covered. See the city approved plans for locations marked in red. I noted that insulation/tenting over the fourth floor corridor piping has been removed in several locations.
|
INSP-Sprinkler Rough-in/Hydro | 1/27/2012 | 1/30/2012 | 1/30/2012 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the specific rooms where sprinkler piping can be covered. The include the rooms at the west end of the third floor.
|
INSP-Sprinkler Rough-in | 1/20/2012 | 1/23/2012 | 1/23/2012 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations at the west end of the fourth floor where the sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 1/12/2012 | 1/13/2012 | 1/13/2012 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the fourth floor west end rooms, marked in red, where the sprinkler piping rough-in passed. The corridor was not included. Piping can not be covered until the tenting has been installed and inspected. I notified the general contractor of this and he stated that the tenting should be complete by tuesday and an inspection request would be called in. I did note that one sprinkler pendant needs to be added due to overspacing from an exterior wall pocket.
|
INSP-Sprinkler Rough-in/Hydro | 12/16/2011 | 12/19/2011 | 12/19/2011 | A | PASS |
Troy Cobbley
|
|
|
The hanger attachment points for the west side of central stairs at the 1st, 2nd and 3rd floors are ok to cover.
|