Permit Information
Permit NumberFIR11-00689
StatusFinaled
Name MICRON TECHNOLOGY INC FP
Site Address 8000 S FEDERAL WAY
Project NameB50-R&D EXPANSION BLD
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of extending a 6” main from the previously installed underground down to the sub fab area system 9. The system also protects the lower portion of the NE and SE stairs. The system is a 6”x4”x1½” grid

Note: See permit FIR11-00301, FIR11-00365, FIR11-0431, FIR11-00448, FIR11-00524, FIR11-00645, FIR11-00658, FIR11-00659 for the review on other portions of this building


Building Department Scope:

Micron Building B50 - R&D Building - To construct a new 111,005 square foot, two story, with 71,855 square foot basement, concrete and steel semiconductor fabrication R & D facility and related site improvements. The first floor level is 89, 435 sq. ft. (60,100 sq. ft. finished and 29,325 sq. ft. unfinished). The second floor is a 21,570 sq. ft. mechanical space (16,170 sq. ft. used and 5,400 square feet future). The basement level (subfab.) has 43,295 sq. ft. finished and 28,560 unfinished. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/20/201211/20/201211/20/2012APASS
DetailsForrest France
INSP-Final Inspection10/17/201210/19/201210/30/2012APART
DetailsForrest France
Final walkthrough completed. Verify conditions per IFC 2009 1803.10.4 at the AE and FE ducts. Plan modifications meet field install.
INSP-Sprinkler Rough-in7/30/20127/31/20127/31/2012APART
DetailsForrest France
Verified added coverage at the stair tower lower landings, coverage adjustments to the east wall sub fab are finished.
INSP-Sprinkler Rough-in7/9/20127/9/20127/12/2012PPART
DetailsForrest France
Rough-in inspection completed.
INSP-Sprinkler Rough-in/Hydro7/2/20127/3/20127/5/2012PPART
DetailsForrest France
System 9 overhead hydrostatic test passed.
INSP-Sprinkler Rough-in4/19/20124/23/20124/23/2012PNR
DetailsForrest France
Preliminary inspection for overhead work at system 9 including partial install of 6" and 4" mains and 1 1/2" branchlines only. Upright heads, seismic bracing, tailbacks, 4" grid main, coverage at stairways and comm rooms are incomplete at this time.