Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR12-00016
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 12754 W LASALLE ST
Project NameSyBase
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of adding, relocating and deleting sprinklers due to new wall and ceiling configuration. The entire building has been reviewed. There are a number of suspended ceiling areas with standard spacing QR sprinklers. There are several large (open to deck) areas that will also be used for light hazard. The open areas have extended coverage SR sprinklers. Since these areas will be light hazard the standard response sprinklers shall be changed to quick response sprinklers. The existing system is a 3”x3”x2” grid.


Building Department Scope:

(SYBASE) To remodel an existing 16,365 sq. ft. office building for a new tenant. Approval Contingent upon complying with the approved plans. Work includes: [construction of full height interior non-bearing walls to create new offices, new men’s locker room, a break room, and two breakout rooms], new system furniture, minor electrical, new plumbing, new accessible doors / hardware, remodel mechanical system, and interior finishes in accordance with ch. 8 of the 2009 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/14/20122/16/20122/16/2012APASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in1/31/20122/1/20122/1/2012APASS
DetailsTroy Cobbley
Sprinkler piping is ok to cover.
INSP-Sprinkler Rough-in1/24/20121/24/20121/24/2012PPASS
DetailsTroy Cobbley
Piping above the hard lids is ok to cover. The new uprights around the full height wall are also complete.