INSP-Final Inspection | 9/18/2012 | 9/18/2012 | 9/18/2012 | A | PASS |
Forrest France
|
|
|
Scope of fire alarm work completed, inspections passed. Permit final approved.
|
INSP-Alarm Testing | 8/15/2012 | 8/15/2012 | 8/15/2012 | A | PART |
Forrest France
|
|
|
Items tested today include MP stations at the fan deck, SD above the mechanical deck NAC, duct detectors at the electrical rooms.
|
INSP-Alarm Testing | 8/1/2012 | 8/1/2012 | 8/2/2012 | A | PART |
Forrest France
|
|
|
System components tested today include vesda zones 8,9,10,11 and 12, added a/v at the SE fab exit, FP system #11 tamper and flow switch, verified outside bell function.
|
INSP-Alarm Testing | 7/18/2012 | 7/19/2012 | 7/19/2012 | P | PART |
Forrest France
|
|
|
Completed testing for MAU shutdown at zones 8,9,10,11, and 12.
|
INSP-Alarm Testing | 7/18/2012 | 7/18/2012 | 7/18/2012 | P | PART |
Forrest France
|
|
|
Completed functional testing and walkthrough of occupant notification at the sub fab, fab, electrical, mechanical, and fan deck areas. One location SE first floor adjacent to the exit enclosure appears lacking in visual coverage.
|
INSP-Alarm Testing | 7/17/2012 | 7/17/2012 | 7/17/2012 | P | PART |
Forrest France
|
|
|
Completed testing for underfloor SD at zones 8,9,10,11, and 12. Also tested MP stations at the sub fab, first floor electrical, exit stairs, and fire riser rooms. SE riser tampers and flows on systems 5,6, and 9 also tested okay. System 11, MAU's, and second floor initiating devices are not yet ready for inspection. Discussed schedule for notification testing at the clean room fab area.
|