INSP-Final Inspection | 5/3/2012 | 5/4/2012 | 5/4/2012 | A | PASS |
Forrest France
|
|
|
Field verified noted conditions for final have been met. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 4/3/2012 | 4/3/2012 | 4/3/2012 | A | PART |
Forrest France
|
|
|
Final pending reliable building heat source to maintain min. temperature at the lower level per NFPA 13.
|
INSP-Final Inspection | 4/2/2012 | 4/2/2012 | 4/2/2012 | P | PART |
Forrest France
|
|
|
Permit final pending ceiling tile and escutcheon in one room at the main level and adequate heating for the lower level to maintain temperature required for wet type sprinkler systems per NFPA 13.
|
INSP-Sprinkler Rough-in | 4/2/2012 | 4/2/2012 | 4/2/2012 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler system modifications are approved for cover. Rough-in passed.
|
INSP-Sprinkler Rough-in | 3/29/2012 | 3/29/2012 | 3/30/2012 | P | NR |
Forrest France
|
|
|
JEREMY Phone #: ###-#### *Note- no access to complete inspection due to jobsite conditions (floor sealant).
|