INSP-Final Inspection | 1/4/2013 | 1/7/2013 | 1/7/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 12/18/2012 | 12/19/2012 | 12/19/2012 | A | CANC |
Troy Cobbley
|
|
|
Could not complete inspection due to problems with the project related fire alarm permits. Also the outside alarm bell needs to be relocated to the side of the building where the FDC has been placed.
|
INSP-Final Inspection | 12/13/2012 | 12/18/2012 | 12/18/2012 | A | FAIL |
Troy Cobbley
|
|
|
Branch line restraints have been installed but the plans have not been resubmitted for review of the pipe route changes in the remote area.
|
INSP-Sprinkler Rough-in/Hydro | 12/6/2012 | 12/6/2012 | 12/6/2012 | P | PART |
Troy Cobbley
|
|
|
Not all of the branchline restraints have been installed as indicated on the city approved plans. Also the 2" riser nipples are shown at 1'-8 1/2" in height but actually measure just over 3'-0" and the riser nipple piping at nodes 14 and 15 as well as being taller, has a 1'-0" offset with an additional 2" elbow. Plans/hydraulic calculations need to be resubmitted for review due to the safety margin being nearly exceeded. All other items appear ok. The forward flush of the backflow easily passed.
|
FIR-Aging Inspection | 10/4/2012 | 10/4/2012 | 10/10/2012 | | NR |
Troy Cobbley
|
|
|
Jeff is following up on status.
|