INSP-Final Inspection | 8/7/2012 | 8/7/2012 | 8/7/2012 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 8/6/2012 | 8/7/2012 | 8/7/2012 | A | FAIL |
Troy Cobbley
|
|
|
Can't final until all of the ceiling tile has been installed.
|
INSP-Final Inspection | 7/21/2012 | 7/24/2012 | 7/24/2012 | P | FAIL |
Troy Cobbley
|
|
|
Permit can be finaled when the ceiling tile has been installed. Interconnection of sprinkler devices with the facp tested except for the south canopy tamper switch that was not shown on the fire alarm plans.
|
INSP-Sprinkler Rough-in/Hydro | 7/18/2012 | 7/19/2012 | 7/19/2012 | A | PASS |
Troy Cobbley
|
|
|
Hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 7/17/2012 | 7/18/2012 | 7/18/2012 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping can be covered. A hydro test is required prior to a final sign off.
|
INSP-Sprinkler Rough-in | 6/27/2012 | 6/27/2012 | 6/27/2012 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping for the new head outside of the "cash room" is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 6/25/2012 | 6/25/2012 | 6/25/2012 | P | PART |
Forrest France
|
|
|
Okay to cover overhead work at the mens and womens restroom including the entry vestibule and two pendent heads to the west of the new partition wall. See plan set for marked and dated areas.
|