INSP-Final Inspection | 4/11/2013 | 4/11/2013 | 4/11/2013 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 4/10/2013 | 4/11/2013 | 4/11/2013 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Supply line flush | 3/18/2013 | 3/19/2013 | 3/19/2013 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
FIR-Aging Inspection | 3/7/2013 | 3/7/2013 | 3/7/2013 | | NR |
Troy Cobbley
|
|
|
work is in progress
|
FIR-Aging Inspection | 11/16/2012 | 11/16/2012 | 11/20/2012 | | NR |
Troy Cobbley
|
|
|
work is in progress
|
INSP-Sprinkler Rough-in | 8/17/2012 | 8/17/2012 | 8/17/2012 | P | PART |
Forrest France
|
|
|
Verified thrust blocking for the relocated 90 and 45 ells at the property line. UG okayed for cover.
|
INSP-Sprinkler Rough-in/Hydro | 8/14/2012 | 8/15/2012 | 8/15/2012 | P | CANC |
Troy Cobbley
|
|
|
Please call 1/2hr prior to inspection. Dale is
the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 8/13/2012 | 8/14/2012 | 8/14/2012 | P | CANC |
Troy Cobbley
|
|
|
Please call 1/2hr prior to inspection. Dale is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 8/13/2012 | 8/13/2012 | 8/13/2012 | P | CANC |
Troy Cobbley
|
|
|
To be resceduled for tomorrow per Dale Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 8/13/2012 | 8/14/2012 | 8/13/2012 | A | CANC |
Troy Cobbley
|
|
|
Please call 1/2 hr prior to inspection. Dale is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 8/8/2012 | 8/9/2012 | 8/9/2012 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground supply piping can be covered. See redline notes on city approved drawings for location.
|
INSP-Sprinkler Rough-in | 7/19/2012 | 7/20/2012 | 7/20/2012 | A | PASS |
Troy Cobbley
|
|
|
Underground supply piping, as marked on plan, is ok to cover.
|