INSP-Final Inspection | 1/22/2013 | 1/22/2013 | 1/22/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. The coverings on two upright heads was removed while I waited.
|
INSP-Final Inspection | 9/26/2012 | 9/27/2012 | 9/27/2012 | A | PART |
Troy Cobbley
|
|
|
Permit finaled. Hanger has been added. Waiting for Phase 2 per Troy Cobbley
|
INSP-Final Inspection | 9/25/2012 | 9/26/2012 | 9/26/2012 | A | FAIL |
Troy Cobbley
|
|
|
Provide hanger on the armover that exceeds 2'.
|
INSP-Conference | 9/14/2012 | 9/17/2012 | 9/17/2012 | A | DONE |
Troy Cobbley
|
|
|
Stopped at job site to see if the last office had been provided with sprinkler protection and to verify that the existing upright coverage was quick responce sprinklers, which they were.
|
INSP-Sprinkler Rough-in | 9/14/2012 | 9/14/2012 | 9/14/2012 | P | PASS |
Troy Cobbley
|
|
|
Piping above the locker rooms is ok to cover. I noted one office on the west side of the tenant space has a ceiling but no pendant sprinkler protection.
|
INSP-Sprinkler Rough-in | 9/11/2012 | 9/12/2012 | 9/12/2012 | A | PASS |
Troy Cobbley
|
|
|
Partial rough to cover for front vestibule hard lid and center gridded area passed and piping is ok to cover.
|