INSP-Final Inspection | 2/22/2013 | 2/26/2013 | 2/26/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 2/20/2013 | 2/22/2013 | 2/22/2013 | A | CANC |
Tim Frost
|
|
|
*Re-assingned by Scott Arellano*
Jonothan Lee Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 11/1/2012 | 11/5/2012 | 11/5/2012 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in | 10/24/2012 | 10/24/2012 | 10/24/2012 | P | PASS |
Troy Cobbley
|
|
|
Tenting has been repaired and the batt insulation installed on the vertical rises. Piping can be covered.
|
INSP-Sprinkler Rough-in | 10/18/2012 | 10/19/2012 | 10/19/2012 | A | FAIL |
Troy Cobbley
|
|
|
I stopped at the job site and found that the tenting had not been repaired or the batt insulation installed.
|
INSP-Sprinkler Rough-in | 10/18/2012 | 10/18/2012 | 10/18/2012 | P | PART |
Troy Cobbley
|
|
|
The heat tape was ok but can not give an approval for cover due to the tenting not being completed in many locations. I also need the batt insulation installed at the vertical risers prior to an approval for cover being given.
|
INSP-Sprinkler Rough-in | 9/28/2012 | 10/1/2012 | 10/1/2012 | A | PART |
Troy Cobbley
|
|
|
First and second floor sprinkler rough-in passed. One pendant was missing on the second floor but can be verified at the next rough-in inspection. Third floor hydraulic calculations need to be re-verified due to pipe routing changes in the remote area. Also tenting has not been done for the third floor or any of the heat trace tape. First and second floor piping can be covered except for the areas where heat trace will need to be inspected.
|