INSP-Final Inspection | 11/7/2012 | 11/8/2012 | 11/8/2012 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 10/18/2012 | 10/22/2012 | 10/22/2012 | P | FAIL |
Troy Cobbley
|
|
|
The outside alarm bell has not been mounted yet therefore it could not be tested by the functional test of the flow switch. Forward flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 9/26/2012 | 9/26/2012 | 9/26/2012 | P | PASS |
Troy Cobbley
|
|
|
Underground and overhead hydro tests passed.
|
INSP-Supply line flush | 9/26/2012 | 9/26/2012 | 9/26/2012 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in | 9/24/2012 | 9/24/2012 | 9/24/2012 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping can be covered. Overhead rough-in for the exposed piping is passed. The approved plans indicate 155 dgree heads to be installed but 200 degree are actually installed, Per Tim Frost this change is acceptable but as-builts will be required prior to a final sign off.
|
INSP-Sprinkler Rough-in | 9/14/2012 | 9/17/2012 | 9/18/2012 | P | PASS |
Troy Cobbley
|
|
|
The cover inspection on the underground installation is passed. Piping can be covered.
|