INSP-Final Inspection | 10/24/2012 | 10/25/2012 | 10/25/2012 | A | PASS |
Forrest France
|
|
|
C/N items are complete. Fire sprinkler permit work passed final inspection.
|
INSP-Final Inspection | 10/17/2012 | 10/22/2012 | 10/22/2012 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test completed satisfactory. Final pending rough-in adjustments.
|
INSP-Sprinkler Rough-in/Hydro | 10/17/2012 | 10/22/2012 | 10/22/2012 | A | FAIL |
Forrest France
|
|
|
Correction items include; missing drum drip at the low conveyor east end, plugged weld outlet in the pendent position to be removed or relocated, raise one upright, noted mixed temperature heads are installed at conveyors (155 deg. at the new equipment and 200 deg. at existing conveyors).
|
INSP-Sprinkler Rough-in/Hydro | 9/28/2012 | 10/1/2012 | 10/3/2012 | A | DEFR |
Forrest France
|
|
|
Intended for FIR12-00314 dry system inspection.
|
INSP-Sprinkler Rough-in/Hydro | 9/27/2012 | 9/27/2012 | 9/28/2012 | P | NR |
Forrest France
|
|
|
Intended for project related dry system permit # FIR12-00314.
|