INSP-Final Inspection | 1/10/2013 | 1/11/2013 | 1/11/2013 | A | PASS |
Forrest France
|
|
|
Fire sprinkler work passed final inspection and walkthrough.
|
INSP-Final Inspection | 1/4/2013 | 1/7/2013 | 1/7/2013 | P | CANC |
Forrest France
|
|
|
Mark J is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 11/13/2012 | 11/14/2012 | 11/14/2012 | A | PART |
Forrest France
|
|
|
Overhead rough-in and tenting inspection completed. DSW heads at the covered porches are in need of adjustment due to soffit construction.
|
INSP-Sprinkler Rough-in/Hydro | 10/29/2012 | 10/30/2012 | 10/30/2012 | P | PART |
Forrest France
|
|
|
OH hydrostatic test passed.
|