Description
The fire sprinkler scope of work consists of 8”x15’± C-900 underground pipe with necessary mechanical joint fittings, yard PIV and thrust blocks until the piping intersects with the basement wall. The piping will then transition to ductile iron. In addition, there will be a second underground pipe 6”x29’± C-900 with necessary mechanical joint fittings, yard PIV and thrust blocks until the piping intersects with the basement wall. The piping will then transition to ductile iron.

Per IFC a require isolation valve is shown as existing in-between the two underground (8” & 6”) connections to the city main.

FIELD INSPECTOR: Please, verify the presents and operational capabilities of the isolation valve.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/27/201312/2/201312/3/2013APASS
DetailsForrest France
UG fire supply line permit finaled.
INSP-Final Inspection11/27/201311/29/201311/27/2013ACANC
DetailsForrest France
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Final Inspection11/19/201311/22/201311/26/2013ANR
DetailsForrest France
Mike B is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro7/26/20137/29/20137/29/2013APASS
DetailsTroy Cobbley
The flush of both underground supply lines passed.
INSP-Supply line flush7/23/20137/25/20137/25/2013ANR
DetailsForrest France
UG Flush-we would like to request this for
7:00 am, Mike Bierman is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro7/23/20137/23/20137/25/2013PPART
DetailsForrest France
UG fire supply line hydrostatic test completed
INSP-Sprinkler Rough-in7/17/20137/18/20137/18/2013ADONE
DetailsTim Frost
Rough in passed. There was no flushing at this time.
INSP-Sprinkler Rough-in7/17/20137/17/20137/17/2013PPART
DetailsTim Frost
One main was roughed in. Two addtional ells were added. The flange still needs to be rodded to the wall. Everthing else appeared ok.



This is an ug inspection. Stan is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus
FIR-Aging Inspection6/28/20136/28/20136/28/2013 DONE
DetailsForrest France
Site work in progress
FIR-Aging Inspection3/5/20133/5/20133/5/2013 DONE
DetailsForrest France
Site work in progress, construction underway.