INSP-Final Inspection | 12/20/2012 | 12/20/2012 | 12/21/2012 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2012 | 12/5/2012 | 12/5/2012 | A | PART |
Forrest France
|
|
|
Noted correction items finished. Remainder of fire sprinkler work passed rough-in. Wall and access door to the fire riser room are not yet constructed.
|
INSP-Sprinkler Rough-in | 12/4/2012 | 12/4/2012 | 12/4/2012 | P | PART |
Forrest France
|
|
|
Okay to cover kitchen area drop ceiling with the exception of adjustments to cover a pocket above the mop sink. Basement area including the new cooler is also approved.
|
INSP-Sprinkler Rough-in/Hydro | 11/26/2012 | 11/26/2012 | 11/26/2012 | A | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 11/5/2012 | 11/6/2012 | 11/6/2012 | A | PART |
Forrest France
|
|
|
See dated plan annotations for notes- common corridor missing one pendent head where grid ceiling is not installed, relocate one head adjacent to wall and finishes, basement storage room spacing needs revised, one blocked head due to new drain piping. Basement cooler and first floor kitchen area grid ceilings and heads are incomplete at this time. Okay to cover modifications above sheetrock ceilings.
|